Sirajganj Combined Cycle Power Plant is a 670MW dual-fuel fired power project. It is located in Barisal, Bangladesh. The project is currently active. It has been developed in multiple phases. Post completion of construction, the project got commissioned in November 2012.
Project Type | Total Capacity (MW) | Active Capacity (MW) | Pipeline Capacity (MW) | Project Status | Project Location | Project Developer | Thermal | 670 | 670 | – | Active | Barisal, Bangladesh | North West Power Generation |
---|
Description
The project is developed and owned by North West Power Generation.
It is a Combined Cycle Gas Turbine (CCGT) power plant. The power plant run on dual-fuel. The primary fuel being used to power the plant is natural gas. In case of shortage of natural gas the plant can also run on High Speed Diesel.
Development Status
The project got commissioned in November 2012.
Power Purchase Agreement
The power generated from the project is sold to Bangladesh Power Development Board under a power purchase agreement.
Contractors Involved
China National Machinery Import & Export was selected to render EPC services for the Sirajganj Combined Cycle Power Plant (Sirajganj Combined Cycle Power Plant Block I GT) project. China National Machinery Import & Export was selected to render EPC services for the Sirajganj Combined Cycle Power Plant (Sirajganj Combined Cycle Power Plant Block I ST) project. China National Machinery Import & Export was selected to render EPC services for the Sirajganj Combined Cycle Power Plant (Sirajganj Combined Cycle Power Plant Block II) project. China National Machinery Import & Export was selected to render EPC services for the Sirajganj Combined Cycle Power Plant (Sirajganj Combined Cycle Power Plant Block III GT) project. China National Machinery Import & Export was selected to render EPC services for the Sirajganj Combined Cycle Power Plant (Sirajganj Combined Cycle Power Plant Block III ST) project. Fujian Electric Power Survey and Design Institute was selected to render EPC services for the Sirajganj Combined Cycle Power Plant (Sirajganj Combined Cycle Power Plant Block II) project. Fujian Electric Power Survey and Design Institute was selected to render EPC services for the Sirajganj Combined Cycle Power Plant (Sirajganj Combined Cycle Power Plant Block III GT) project. Fujian Electric Power Survey and Design Institute was selected to render EPC services for the Sirajganj Combined Cycle Power Plant (Sirajganj Combined Cycle Power Plant Block III ST) project.
Sirajganj Combined Cycle Power Plant (Sirajganj Combined Cycle Power Plant Block I GT) is equipped with Siemens SGT5-2000E gas turbine. The phase consists of 1 gas turbine with 150MW nameplate capacity.
Sirajganj Combined Cycle Power Plant (Sirajganj Combined Cycle Power Plant Block I ST) is equipped with DEC Dongfang Electric Machinery steam turbine. The phase consists of 1 steam turbine with 75MW nameplate capacity.
Sirajganj Combined Cycle Power Plant (Sirajganj Combined Cycle Power Plant Block II) is equipped with DEC Dongfang Electric Machinery steam turbine. The Dual-Fuel fired phase consists 1 steam turbine.
Sirajganj Combined Cycle Power Plant (Sirajganj Combined Cycle Power Plant Block II) is equipped with Siemens gas turbine. The Dual-Fuel fired phase consists 1 gas turbine.
Sirajganj Combined Cycle Power Plant (Sirajganj Combined Cycle Power Plant Block III GT) is equipped with Siemens SGT5-2000E gas turbine. The phase consists of 1 gas turbine with 141MW nameplate capacity.
Sirajganj Combined Cycle Power Plant (Sirajganj Combined Cycle Power Plant Block III ST) is equipped with DEC Dongfang Electric Machinery steam turbine. The phase consists of 1 steam turbine with 79MW nameplate capacity.
Siemens supplied electric generator for the Sirajganj Combined Cycle Power Plant (Sirajganj Combined Cycle Power Plant Block I GT).
DEC Dongfang Electric Machinery supplied electric generator for the Sirajganj Combined Cycle Power Plant (Sirajganj Combined Cycle Power Plant Block I ST).
Siemens supplied electric generator for the Sirajganj Combined Cycle Power Plant (Sirajganj Combined Cycle Power Plant Block II).
DEC Dongfang Electric Machinery supplied electric generator for the Sirajganj Combined Cycle Power Plant (Sirajganj Combined Cycle Power Plant Block II).
Siemens supplied SGen-100A electric generator for the Sirajganj Combined Cycle Power Plant (Sirajganj Combined Cycle Power Plant Block III GT).
DEC Dongfang Electric Machinery supplied electric generator for the Sirajganj Combined Cycle Power Plant (Sirajganj Combined Cycle Power Plant Block III ST).
Methodology
All power projects included in this report are drawn from GlobalData’s Power Intelligence Center. The information regarding the project parameters is sourced through secondary information sources such as electric utilities, equipment manufacturers, developers, project proponent’s – news, deals and financial reporting, regulatory body, associations, government planning reports and publications. Wherever needed the information is further validated through primary from various stakeholders across the power value chain and professionals from leading players within the power sector.