Sodra Midsjobanken is a 1,600MW offshore wind power project. It is planned in Baltic Sea, Sweden. The project is currently in permitting stage. It will be developed in single phase. Post completion of the construction, the project is expected to get commissioned in 2027.

Project Type Total Capacity (MW) Active Capacity (MW) Pipeline Capacity (MW) Project Status Project Location Project Developer
Offshore 1,600 1,600 Permitting Sweden RWE Renewables Sweden

Description

The project is being developed and currently owned by RWE Renewables Sweden.

The project is expected to generate 6,000,000MWh of electricity. The project cost is expected to be around $5,204.8m. The project will be spread over an area of 200km². The turbines will be mounted on a fixed type foundation.

The wind power project consists of 120 turbines.

Development Status

Post completion of the construction, the project is expected to get commissioned in 2027.

Methodology

All power projects included in this report are drawn from GlobalData’s Power Intelligence Center. The information regarding the project parameters is sourced through secondary information sources such as electric utilities, equipment manufacturers, developers, project proponent’s – news, deals and financial reporting, regulatory body, associations, government planning reports and publications. Wherever needed the information is further validated through primary from various stakeholders across the power value chain and professionals from leading players within the power sector.