Steti Biomass Power Plant is a 25MW biopower project. It is located in Usti nad Labem, Czech Republic. The project is currently active. It has been developed in single phase. Post completion of construction, the project got commissioned in 1998.
Project Type | Total Capacity (MW) | Active Capacity (MW) | Pipeline Capacity (MW) | Project Status | Project Location | Project Developer | Biopower | 25 | 25 | – | Active | Usti nad Labem, Czech Republic |
---|
Description
The process of combustion has been adopted in this co-firing project to release the stored energy from the feed. Wood by-product is used as a feedstock to power the project.
Development Status
The project got commissioned in 1998.
Contractors Involved
Sumitomo SHI FW Energia supplied steam boiler for the project. The temperature witnessed inside the boiler is around 535°C. The steam is pressurized inside the boiler at 34bar.
Methodology
All power projects included in this report are drawn from GlobalData’s Power Intelligence Center. The information regarding the project parameters is sourced through secondary information sources such as electric utilities, equipment manufacturers, developers, project proponent’s – news, deals and financial reporting, regulatory body, associations, government planning reports and publications. Wherever needed the information is further validated through primary from various stakeholders across the power value chain and professionals from leading players within the power sector.