Receive our newsletter – data, insights and analysis delivered to you
  1. Market Data
January 5, 2022

Windpark Dornum, Germany

By Carmen

Windpark Dornum is a 66.85MW onshore wind power project. It is located in Lower Saxony, Germany. The project is currently active. It has been developed in multiple phases. Post completion of construction, the project got commissioned in June 2011.

Project Type Total Capacity (MW) Active Capacity (MW) Pipeline Capacity (MW) Project Status Project Location Project Developer
Onshore 66.85 66.85 Active Lower Saxony, Germany Pommer & Schwarz EmeuerbareEnergienGesellschaft

Description

The project was developed by Pommer & Schwarz EmeuerbareEnergienGesellschaft.

The Windpark Dornum (Windpark Dornum – Phase I), has 64m high towers.

The Windpark Dornum (Windpark Dornum – Phase II), has 113.5m high towers.

The Windpark Dornum (Windpark Dornum – Phase III), has 138m high towers.

Content from our partners
How Hengst helped to keep Germany’s charity “star singers” shining
How one power station prevented frequent shutdowns with three-stage air filtration
Reimagining the carbon problem

The Windpark Dornum (Windpark Dornum – Phase IV), has 135m high towers.

The Windpark Dornum (Windpark Dornum – Phase V), has 135m high towers.

Development Status

The project is currently active. The project got commissioned in June 2011.

Contractors Involved

Windpark Dornum (Windpark Dornum – Phase I) is equipped with Enercon E-70 E4/ 2,300 kW turbines. The phase consists of 15 turbines with 2.3MW nameplate capacity.

Windpark Dornum (Windpark Dornum – Phase II) is equipped with Enercon E-70 E4/ 2,300 kW turbine. The phase consists of 1 turbine with 2.3MW nameplate capacity.

Windpark Dornum (Windpark Dornum – Phase III) is equipped with Enercon E-92 / 2,350 kW turbines. The phase consists of 5 turbines with 2.35MW nameplate capacity.

Windpark Dornum (Windpark Dornum – Phase IV) is equipped with Enercon E-101 / 3,050 kW turbines. The phase consists of 3 turbines with 3.05MW nameplate capacity.

Windpark Dornum (Windpark Dornum – Phase V) is equipped with Enercon E-101 / 3,050 kW turbines. The phase consists of 3 turbines with 3.05MW nameplate capacity.

Methodology

All power projects included in this report are drawn from GlobalData’s Power Intelligence Center. The information regarding the project parameters is sourced through secondary information sources such as electric utilities, equipment manufacturers, developers, project proponent’s – news, deals and financial reporting, regulatory body, associations, government planning reports and publications. Wherever needed the information is further validated through primary from various stakeholders across the power value chain and professionals from leading players within the power sector.

Related Companies

NEWSLETTER Sign up Tick the boxes of the newsletters you would like to receive. The top stories of the day delivered to you every weekday. A weekly roundup of the latest news and analysis, sent every Wednesday. The power industry's most comprehensive news and information delivered every month.
I consent to GlobalData UK Limited collecting my details provided via this form in accordance with the Privacy Policy
SUBSCRIBED

THANK YOU