Xibaipo Coal Fired Power Plant is a 2,400MW coal fired power project. It is located in Hebei, China. The project is currently active. It has been developed in multiple phases. Post completion of construction, the project got commissioned in 1993.
Project Type | Total Capacity (MW) | Active Capacity (MW) | Pipeline Capacity (MW) | Project Status | Project Location | Project Developer | Thermal | 2,400 | 2,400 | – | Active | Hebei, China |
---|
Description
The project is currently owned by Hebei Xibaipo Power Generation.
It is a steam turbine power plant.
Development Status
The project got commissioned in 1993.
Contractors Involved
Xibaipo Coal Fired Power Plant (Xibaipo Coal Fired Power Plant I Unit I) is equipped with Harbin Steam Turbine Factory N330-16.7/537/537 steam turbine. The phase consists of 1 steam turbine with 300MW nameplate capacity.
Xibaipo Coal Fired Power Plant (Xibaipo Coal Fired Power Plant I Unit II) is equipped with Harbin Steam Turbine Factory N330-16.7/537/537 steam turbine. The phase consists of 1 steam turbine with 300MW nameplate capacity.
Xibaipo Coal Fired Power Plant (Xibaipo Coal Fired Power Plant I Unit III) is equipped with Harbin Steam Turbine Factory N330-16.7/537/537 steam turbine. The phase consists of 1 steam turbine with 300MW nameplate capacity.
Xibaipo Coal Fired Power Plant (Xibaipo Coal Fired Power Plant I Unit IV) is equipped with Harbin Steam Turbine Factory N330-16.7/537/537 steam turbine. The phase consists of 1 steam turbine with 300MW nameplate capacity.
Xibaipo Coal Fired Power Plant (Xibaipo Coal Fired Power Plant II Unit I) is equipped with Harbin Steam Turbine Factory N600-24.2/538/566 steam turbine. The phase consists of 1 steam turbine with 600MW nameplate capacity.
Xibaipo Coal Fired Power Plant (Xibaipo Coal Fired Power Plant II Unit II) is equipped with Harbin Steam Turbine Factory N600-24.2/538/566 steam turbine. The phase consists of 1 steam turbine with 600MW nameplate capacity.
Harbin Electric Machinery supplied QFSN-300-2 electric generator for the Xibaipo Coal Fired Power Plant (Xibaipo Coal Fired Power Plant I Unit I).
Harbin Electric Machinery supplied QFSN-300-2 electric generator for the Xibaipo Coal Fired Power Plant (Xibaipo Coal Fired Power Plant I Unit II).
Harbin Electric Machinery supplied QFSN-300-2 electric generator for the Xibaipo Coal Fired Power Plant (Xibaipo Coal Fired Power Plant I Unit III).
Harbin Electric Machinery supplied QFSN-300-2 electric generator for the Xibaipo Coal Fired Power Plant (Xibaipo Coal Fired Power Plant I Unit IV).
Harbin Electric Machinery supplied QFSN 600-2YHG electric generator for the Xibaipo Coal Fired Power Plant (Xibaipo Coal Fired Power Plant II Unit I).
Harbin Electric Machinery supplied QFSN 600-2YHG electric generator for the Xibaipo Coal Fired Power Plant (Xibaipo Coal Fired Power Plant II Unit II).
Babcock & Wilcox Beijing supplied steam boiler for the Xibaipo Coal Fired Power Plant (Xibaipo Coal Fired Power Plant I Unit I).
Babcock & Wilcox Beijing supplied steam boiler for the Xibaipo Coal Fired Power Plant (Xibaipo Coal Fired Power Plant I Unit II).
Babcock & Wilcox Beijing supplied steam boiler for the Xibaipo Coal Fired Power Plant (Xibaipo Coal Fired Power Plant I Unit III).
Babcock & Wilcox Beijing supplied steam boiler for the Xibaipo Coal Fired Power Plant (Xibaipo Coal Fired Power Plant I Unit IV).
Babcock & Wilcox Beijing supplied steam boiler for the Xibaipo Coal Fired Power Plant (Xibaipo Coal Fired Power Plant II Unit I).
Babcock & Wilcox Beijing supplied steam boiler for the Xibaipo Coal Fired Power Plant (Xibaipo Coal Fired Power Plant II Unit II).
Methodology
All power projects included in this report are drawn from GlobalData’s Power Intelligence Center. The information regarding the project parameters is sourced through secondary information sources such as electric utilities, equipment manufacturers, developers, project proponent’s – news, deals and financial reporting, regulatory body, associations, government planning reports and publications. Wherever needed the information is further validated through primary from various stakeholders across the power value chain and professionals from leading players within the power sector.