Yutang is a 75MW hydro power project. It is located on Furong river/basin in Guizhou, China. The project is currently active. It has been developed in single phase. The project construction commenced in 2004 and subsequently entered into commercial operation in 2005.

Project Type Total Capacity (MW) Active Capacity (MW) Pipeline Capacity (MW) Project Status Project Location Project Developer
Hydropower 75 75 Active Guizhou, China Guizhou Beiyuan Electric Power

Description

The project was developed by Guizhou Beiyuan Electric Power. The project is currently owned by Guizhou Qianyuan Power with a stake of 50.25%, Guizhou Wujiang Hydropower Development Limited Liability and Guizhou Yayuan Industry and Trade.

Yutang is a reservoir based project. The hydro reservoir capacity is 122.4 million cubic meter. The project generated 312.8 GWh of electricity.

Development Status

The project construction commenced in 2004 and subsequently entered into commercial operation in 2005.

Power Purchase Agreement

The power generated from the project is sold to China Southern Power Grid under a power purchase agreement.

Contractors Involved

Sichuan Dongfeng Motor was selected as the turbine supplier for the hydro power project. The company provided 2 units of francis turbines, each with 37.5MW nameplate capacity.

Sichuan Dongfeng Motor supplied 2 electric generators for the project. The generator capacity is 37.5 MVA.

Methodology

All power projects included in this report are drawn from GlobalData’s Power Intelligence Center. The information regarding the project parameters is sourced through secondary information sources such as electric utilities, equipment manufacturers, developers, project proponent’s – news, deals and financial reporting, regulatory body, associations, government planning reports and publications. Wherever needed the information is further validated through primary from various stakeholders across the power value chain and professionals from leading players within the power sector.