Canada’s independent power producers Maxim Power has completed the upgrade of its Milner II 204MW power plant in Alberta, Canada, with support from GE.

As part of the upgrade, Maxim Power selected GE to re-power the coal facility using natural gas.

Maxim Power president and chief operating officer Bob Emmott said: “Canada is part of the international community moving toward a decarbonised future, with Alberta committed to a phase-out of coal power by 2030.

“We were faced with the reality of shuttering the facility or re-powering it with natural gas, the cleanest burning fossil fuel, emitting less than half the CO₂ of a coal plant, significantly lower nitrous oxides and particulate matter, no mercury, and essentially no sulfur oxides, and we decided to turn to GE to help us transition the facility to natural gas.”

For the project, GE upgraded Maxim Power’s Milner II plant with the installation of a 7F.05 gas turbine.

How well do you really know your competitors?

Access the most comprehensive Company Profiles on the market, powered by GlobalData. Save hours of research. Gain competitive edge.

Company Profile – free sample

Thank you!

Your download email will arrive shortly

Not ready to buy yet? Download a free sample

We are confident about the unique quality of our Company Profiles. However, we want you to make the most beneficial decision for your business, so we offer a free sample that you can download by submitting the below form

By GlobalData
Visit our Privacy Policy for more information about our services, how we may use, process and share your personal data, including information of your rights in respect of your personal data and how you can unsubscribe from future marketing communications. Our services are intended for corporate subscribers and you warrant that the email address submitted is your corporate email address.

Following the upgrade, the power plant is said to have become the largest simple-cycle natural gas-fired unit in Alberta.

The upgrade is part of Maxim Power’s efforts to transition to natural gas and also supports Alberta and Canada’s efforts towards decarbonisation through a coal-to-gas transition.

GE noted that Maxim Power’s M II natural gas-fired power plant is delivering power to the Alberta grid near Grand Cache using natural gas with 50% fewer emissions than that of a coal-fired facility.

The company also offered relocation support with a DLN2.6+ upgrade.

GE Gas Power Americas vice-president Eric Gray said: “In North America, energy usage has been changing for many years: as the availability of natural gas and renewables has increased, and the use of coal has declined.

“Alberta is implementing a broad coal phase-out plan and we are honoured to support power plant operators, like Maxim Power, to embrace the flexibility gas technology offers to complement renewables including solar and wind.”