First Wind has completed the construction of the 102MW Milford Wind Corridor Phase II project (Milford II) in the US. The facility, which features 68 1.5MW GE turbines, is located nearby the 204MW Milford I project in the counties of Millard and Beaver, Utah. Under a power pu

First Wind has completed the construction of the 102MW Milford Wind Corridor Phase II project (Milford II) in the US.

The facility, which features 68 1.5MW GE turbines, is located nearby the 204MW Milford I project in the counties of Millard and Beaver, Utah.

Under a power purchase agreement with Southern California Public Power Authority, the power generated by the facility will be supplied to the Los Angeles Department of Water and Power and Glendale Water and Power.

The combined 306MW capacity generated by Milford I and Milford II will be sufficient to power about 64,000 homes.