Xcel Energy receives approval to buy 698MW wind power

Xcel Energy has received approval from the New Mexico Public Regulation Commission for its power purchase agreements with developers for 698MW of wind energy for its Texas-New Mexico system.

By admin-demo

Xcel Energy has received approval from the New Mexico Public Regulation Commission for its power purchase agreements with developers for 698MW of wind energy for its Texas-New Mexico system.

The company can now buy the wind power from projects planned for Roosevelt County, New Mexico; Hansford and Ochiltree counties, Texas, and Dewey and Blaine counties, Oklahoma.

The company claims these agreements will save customers in Texas and New Mexico approximately $590m in fuel costs over 20 years.

Earlier in July 2013, Southwestern Public Service Company, a subsidiary of Xcel Energy, had sought approval for 20-year power purchase agreements with three wind power plants, which are expected to be operational by the end of December 2014.

"The company claims these agreements will save customers in Texas and New Mexico approximately $590m in fuel costs over 20 years."

The company signed two agreements with NextEra Energy Resources’s 199MW Mammoth Plains Wind Energy Center in Oklahoma and 249MW Palo Duro Wind Energy Center in Texas.

The company had signed the third agreement with Infinity Wind Resources to buy 250MW from Roosevelt Wind Ranch in Roosevelt County, New Mexico.

Mammoth Plains will feature 117 1.7MW wind turbines and will produce an estimated annual wind power of 996,000MWh, while Palo Duro will include 147 1.7MW turbines and generate an estimated annual wind power of 1,180,000MWh.

The developer has not finalised the type and number of turbines for Roosevelt Wind Ranch, which is estimated to produce 1,060,000MWh of power annually. However, the project may include: 108 2.3MW turbines (248.4MW), or 147 1.7MW turbines (249.9MW), or 125 2MW turbines (250MW).

Southwestern Public Service Company president and CEO Riley Hill said the company has already exceeded requirements of renewable portfolio standards in both New Mexico and Texas and the additional capacity it purchased is primarily for economic reasons.

Hill said: "The energy purchased from these facilities has been contracted at a price that is less than the price of power generated at some older natural gas-fueled power plants.

"Additionally, the expected output of the facilities will displace power generated by fossil fuels, which helps us control emissions, lower fuel costs, save water and lower the cost of environmental compliance over time."


Energy

Related Companies

NEWSLETTER Sign up Tick the boxes of the newsletters you would like to receive. The top stories of the day delivered to you every weekday. A weekly roundup of the latest news and analysis, sent every Wednesday. The power industry's most comprehensive news and information delivered every month.
I consent to GlobalData UK Limited collecting my details provided via this form in accordance with the Privacy Policy
SUBSCRIBED

THANK YOU

Thank you for subscribing to Power Technology