Lagisza Power Plant Supercritical Circulating Fluidised Bed, Poland

Email-Icon
 
Print-Icon
 
Link-to-us
key facts
Key Data
Organisation
Poludniowy Koncern Energetyczny (PKE)
Location
Lagisza, southern Poland
Type of Facility (technologies)
Supercritical circulating fluidised bed
Project Cost
Around €150m
Project Confirmed
February 2003
Pre-engineering Work
Started March 2003
Contract Signed
December 2003

Construction is nearing completion on the world's first supercritical circulating fluidised bed (CFB) project at Lagisza, in Poland. Valued at some €150m, the project covers a 460MWe boiler island for a power plant at Lagisza. Work started at the site in February 2006 and, at June 2007, the boiler island was about 20% complete. The order was placed by Poland's largest utility, Poludniowy Koncern Energetyczny (PKE), and the unit will be the world's largest CFB design of any type built so far.

"The Lagisza unit will be the world's largest CFB design of any type built so far."

The new unit is being built alongside PKE's existing 840MWe power station at Lagisza (northeast of Katowice in Upper Silesia). It is part of an ongoing programme by PKE to replace outdated capacity with modern, high-efficiency plant. Operating seven other power stations in southern and western Poland, PKE is the country's largest electricity utility, with 5,056MW of installed generating capacity.

Foster Wheeler Energia Oy and its Polish subsidiary, Foster Wheeler Energia Polska Sp zoo are jointly executing the contract. Pre-engineering work started in March 2003. Notice to proceed was gained in the summer of 2003 and plant start-up should take place early in 2009.

FLUIDISED BED COMBUSTION

The Lagisza plant will have efficient fuel usage and low emissions, fully meeting the requirements of the EU's new large combustion plant (LCP) directive. Total plant efficiency will be above 43%.

Supercritical steam cuts fuel use per GWh of electricity generated by some 5% over conventional drum-based boilers. An equivalent increase in fuel efficiency has typically taken up to ten years of cumulative developmental work to achieve, so achieving this improvement in a single step is a major achievement. A modular design approach will enable supplier Foster Wheeler to offer even larger units of the same type in the future.

Circulating fluidised beds burn many fuels cleanly, including waste coals, petroleum coke, and even shredded automobile tires. They have been installed at chemical plants, steel plants and other industrial facilities around the world. They range in size from relatively small industrial units to large "utility-scale" installations rated at hundreds of megawatts.

The low combustion temperature (~850°C) of the CFB minimises NOx and permits optimum sulphur capture, while the flywheel of circulating solids permits significant variations in fuel properties. CFB-furnace heat fluxes are also less than half those of peak heat fluxes in pulverised-coal furnaces. As a result, low mass-flow rates can be used in the furnace tubes without concern for tube overheating.

The flywheel of circulating solids also provides relatively uniform heat-absorption rates, which minimise concerns for heat absorption unbalances. Foster Wheeler, which supplies the CFB, uses a Siemens Benson vertical OTU (once-through unit).

OTU BOILERS AND STEAM FLOW RATE CONTROL

Boilers for utility power generation are either "drum" or "once-through" types, referring to how water is circulated to cool the tubing that forms the furnace enclosure. Heat is transferred through the tubes and into the water passing through to generate steam. In drum-type units, the steam-flow rate is controlled by the fuel-firing rate.

Superheat steam temperature is determined by properly sizing the superheater heat-transfer surface, and is controlled by spraywater. In a once-through type boiler, the steam-flow rate is established by the boiler feedwater pump and the superheat steam temperature is controlled by the fuel-firing rate.

Since the once-through boiler does not rely on the density difference between steam and water to provide proper circulation and cooling of the furnace enclosure tubes, it can be operated at supercritical (more than 220bar / 3,200psia) pressures. Then, greater steam-turbine efficiency improves plant heat rates. Efficiency increases by roughly 3% on making the transition from 167bar, the standard for drum boilers, to 250bar without significant increases in investment costs.

With about 1,000 units, the Benson boiler is the most common implementation of the once-through design.

"With about 1,000 units, the Benson boiler is the most common implementation of the once-through design."

LARGEST POLISH UTILITY COMPANY

The state-owned Poludniowy Koncern Energetyczny (PKE) is Poland's largest utility, generating about 18% of the power and 16% of the heat produced in Poland. The Lagisza project is the largest energy-sector investment to be financed without being guaranteed by long-term contracts.

PKE is using its own capital, state funds and money from assorted Polish environmental protection funds.

PKE negotiated with Polish power grid operator PSE for access to its high-voltage transmission system, allowing the company to export the power generated from the new Lagisza power block.



Expand Image Expand Image
Foster Wheeler supplied the circulating fluidised bed, which first gasifies the fuel.



Expand Image Expand Image
Firing concepts for the Siemens Benson vertical OTU (once-through unit) used by Foster Wheeler.



Expand Image Expand Image
Sliding pressure reduces thermal stresses in the turbine.



Expand Image Expand Image
The Siemens Benson test rig is used for intensive R&D for two-phase flow.



Post to:
Delicious  
Digg  
reddit  
Facebook  
StumbleUpon  

Suppliers
WENDTDEKOMTE

Home
New On This Site
Products & Services
Company A-Z
Industry Projects
Special Reports
White Papers
Jobs & Careers
Industry News
Events & Exhibitions
Newsletter Archive
Newsletter Sign-Up
Advertise With Us
About Us
Client Area


RSS What is RSS
The website for the power industry