Reihoku Thermal Power Station is a 1,400MW coal fired power project. It is located in Kumamoto, Japan. The project is currently active. It has been developed in multiple phases. Post completion of construction, the project got commissioned in December 1995.

Project Type Total Capacity (MW) Active Capacity (MW) Pipeline Capacity (MW) Project Status Project Location Project Developer
Thermal 1,400 1,400 Active Kumamoto, Japan

Description

The project is currently owned by Kyushu Electric Power.

It is a steam turbine power plant.

Development Status

The project got commissioned in December 1995.

GlobalData Strategic Intelligence

US Tariffs are shifting - will you react or anticipate?

Don’t let policy changes catch you off guard. Stay proactive with real-time data and expert analysis.

By GlobalData

Contractors Involved

Reihoku Thermal Power Station (Reihoku Thermal Power Station Unit I) is equipped with Toshiba Energy Systems and Solutions steam turbine. The phase consists of 1 steam turbine with 700MW nameplate capacity.

Reihoku Thermal Power Station (Reihoku Thermal Power Station Unit II) is equipped with Toshiba Energy Systems and Solutions steam turbine. The phase consists of 1 steam turbine with 700MW nameplate capacity.

Toshiba Energy Systems and Solutions supplied electric generator for the Reihoku Thermal Power Station (Reihoku Thermal Power Station Unit I).

Toshiba Energy Systems and Solutions supplied electric generator for the Reihoku Thermal Power Station (Reihoku Thermal Power Station Unit II).

IHI supplied steam boiler for the Reihoku Thermal Power Station (Reihoku Thermal Power Station Unit I).

Mitsubishi Power supplied steam boiler for the Reihoku Thermal Power Station (Reihoku Thermal Power Station Unit II).

Methodology

All power projects included in this report are drawn from GlobalData’s Power Intelligence Center. The information regarding the project parameters is sourced through secondary information sources such as electric utilities, equipment manufacturers, developers, project proponent’s – news, deals and financial reporting, regulatory body, associations, government planning reports and publications. Wherever needed the information is further validated through primary from various stakeholders across the power value chain and professionals from leading players within the power sector.