The Sandow Lakes Lee County Gas Fired Power Plant is 1,200MW gas fired power project. It is planned in Texas, the US. According to GlobalData, who tracks and profiles over 170,000 power plants worldwide, the project is currently at the permitting stage. It will be developed in a single phase. The project construction is likely to commence in 2025 and is expected to enter into commercial operation in 2028. Buy the profile here.
Description
The project is being developed and currently owned by Sandow Lakes Energy. The company has a stake of 100%.
It is a Combined Cycle Gas Turbine (CCGT) power plant.
Development status
The project construction is expected to commence from 2025. Subsequent to that it will enter into commercial operation by 2028.
Contractors involved
Siemens Energy will be the turbine supplier for the Gas fired project. The company is expected to provide 2 units of SGT6-9000HL gas turbines.
For more details on Sandow Lakes Lee County Gas Fired Power Plant, buy the profile here.
About Sandow Lakes Energy
Sandow Lakes Energy Co LLC specialises in the construction of power plants using natural gas for the generation and transmission of electricity. The company is headquartered in New Castle, Delaware, the US.