The hydropower projects approaching commissioning in 2026 reflect a sector characterised by long development cycles and uneven delivery rather than distinct expansion phases. New capacity continues to emerge from a combination of pumped storage schemes responding to system flexibility needs, conventional projects that have taken many years to reach completion and smaller additions designed to make use of existing infrastructure. For engineers, the significance of the 2026 pipeline lies less in aggregate capacity and more in the technical and organisational challenges associated with bringing complex projects into service under changing grid, regulatory and market conditions.
Across these categories, the critical path to commercial operation is dominated by electro-mechanical delivery, control systems and grid readiness. Civil works are largely complete for many of the projects discussed here; the remaining risks lie in commissioning sequencing, protection coordination and the ability to demonstrate stable operation under real system conditions.
Tehri pumped storage project, India
India’s Tehri Pumped Storage Project is one of the most clearly defined 2026 commissioning cases. Developed by THDC India as part of the wider Tehri hydro complex, the 1GW scheme comprises four 250MW reversible units and is widely described as the country’s first variable-speed pumped storage installation.
Download sample pages of selected reports
Explore a selection of report samples we have handpicked for you. Get a preview of the insights inside. Download your free copy today.
The project has already seen initial units enter service, with the remaining units scheduled for commissioning through late 2025 and January 2026. From an engineering perspective, the significance of Tehri lies in its control and grid integration requirements. Variable-speed operation demands careful tuning of power electronics, turbine-generator control systems and protection schemes, particularly during transitions between pumping and generating modes.
As with many large pumped storage projects, the final commissioning phase is less about hydraulic structures and more about system behaviour: transient response in long waterways, interaction with automatic generation control and the demonstration of fast response services under grid operator supervision.
Tidong hydropower project, India
The 150MW Tidong project in Himachal Pradesh represents a different segment of the 2026 pipeline. As a run-of-river (RoR) scheme in a Himalayan setting, its delivery challenges have been shaped by access constraints, complex geology and long development timelines. Public disclosures indicate that the project is expected to reach completion and begin operations in 2026, with October frequently cited as a target date.
For engineers, the late-stage risks at Tidong are typical of high-head RoR projects: final completion of waterways and pressure shafts, reliable operation of intake and sediment management systems, and grid evacuation through often-congested mountain corridors. Commissioning programmes for such projects must also account for seasonal hydrology, which can constrain the available window for wet testing and full-load trials.

Shongtong-Karcham hydropower project, India
The Shongtong-Karcham project has been under development for many years and is emblematic of several large Himalayan schemes that are now approaching completion. The state government of Himachal Pradesh has set November 2026 as a target for completion of the 450MW project.
For engineers, projects of this type often face distinctive late-phase challenges. Extended construction periods can require revalidation of civil structures, refurbishment of partially completed works and careful management of interface risks where contractors or suppliers have changed. Underground powerhouses and long headrace tunnels demand renewed attention to drainage, support systems and long-term stability as commissioning approaches.
Cruachan pumped storage, Scotland
Not all capacity entering service in 2026 will come from new construction. At Cruachan in Scotland, unit upgrades and modernisation works are expected to see refurbished machines commissioned across 2026 and 2027. While capacity additions from such projects may be modest, their system value can be substantial.
Commissioning upgraded units in an operating pumped storage plant requires careful outage planning and temporary operational configurations. Engineers must manage the integration of new control systems with legacy equipment, ensure protection schemes remain robust throughout transitional states and validate performance across a wider operating envelope than originally envisaged when the plant was first built.

Balanga Dam small hydropower project, Nigeria
At the smaller end of the spectrum, the Balanga dam project in Nigeria illustrates the continued relevance of small hydropower additions. The EU-funded scheme, with an installed capacity of around 620kW, is scheduled for commissioning in March 2026.
Although small in scale, such projects often face disproportionate grid-related challenges. Weak local networks, protection coordination, voltage control and operational resilience can all influence commissioning timelines. For engineers working in similar contexts, Balanga underscores the importance of integrating electrical and grid considerations early, even for relatively modest installations.
Rioseco dam project, Spain
In Spain, EDP is developing a 3.2MW hydropower plant at the Rioseco dam in Sobrescobio, Asturias, equipped with two 1.6MW cross-flow turbines and scheduled for commissioning in 2026. Dam-toe projects of this type are increasingly attractive in mature hydro markets, offering incremental capacity with limited new civil works.
From an engineering perspective, the key considerations lie in hydraulic integration with existing dam operations, sediment and debris management, and ensuring that the new powerhouse does not compromise flood routing or dam safety instrumentation. Turbine selection reflects a balance between efficiency, operational flexibility and maintenance practicality under variable head conditions.
Kulanak hydropower project, Kyrgyzstan
The 100MW Kulanak project in Kyrgyzstan is another mid-sized scheme due to be commissioned in 2026. In Central Asian systems, hydropower projects often play a dual role in domestic supply and regional power balancing.
Engineering risks at this scale are frequently tied to sediment management, seasonal hydrology and the readiness of transmission infrastructure. As commissioning approaches, coordination between plant readiness and grid availability becomes critical, particularly where export or interconnection arrangements are involved.
Caculo Cabaça hydropower project, Angola
Caculo Cabaça remains one of the largest hydropower projects in Africa, with some sources continuing to reference 2026 as a target for commissioning. However, reported timelines vary, and the project highlights the uncertainty that can surround late-stage delivery on very large schemes.
For engineers, the distinction between civil completion, first unit synchronisation and full commercial operation is especially important at this scale. Transformer and geographic information systems delivery, system strength for initial energisation, staged unit commissioning, and operations and maintenance readiness all influence how quickly a project can move from first power to sustained, reliable operation.
Unlock up to 35% savings on GlobalData reports
Use the code at checkout in the report store
-
20% OFF
Buy 2 reports
Use code:
Bundle20
-
25% OFF
Buy 3 reports
Use code:
Bundle25
-
30% OFF
Buy 4 reports
Use code:
Bundle30
-
35% OFF
Buy 5+ reports
Use code:
Bundle35
Valid on all reports priced $995 and above. Cannot be combined with other offers.
Still deciding what will work best for your business?
Ask our experts for help.
Enquire before buying