Vattenfall and Copenhagen Infrastructure Partners (CIP), via their joint venture Zeevonk, have chosen Siemens Gamesa to supply 69 turbines for Phase I of their Zeevonk offshore wind project in the Dutch North Sea.

Zeevonk Phase I is expected to deliver around 1GW of offshore wind capacity.

Discover B2B Marketing That Performs

Combine business intelligence and editorial excellence to reach engaged professionals across 36 leading media platforms.

Find out more

The wind farm is being developed across an area of 196km², located 63 to 84km from the Dutch coast.

Each turbine, with SG 15-236 model, will have a nominal capacity of 15MW.

In addition to supplying turbines, Siemens Gamesa will offer long-term service and maintenance under a separate agreement.

This includes full operational support and monitoring of the wind farm to maintain availability and efficiency.

These agreements indicate that Zeevonk has now secured all major supplier contracts for the construction of Phase I.

Vattenfall offshore head David Flood said: “Zeevonk is a large and ambitious project and selecting Siemens Gamesa as turbine supplier is an important step towards execution.

“Strong supplier partnerships are essential to delivering a competitive offshore wind project on this scale. Together with our partners, we are now putting the key building blocks in place to a successful delivery of Zeevonk.”

Earlier supplier deals for this stage include TKF for inter-array cables, EEW Group for foundations, DEME for installation vessels, and Boskalis for cable installation.

The turbines for Zeevonk Phase I feature direct drive technology and a rotor diameter of 236m, with each blade measuring 115m. Each turbine’s blades sweep an area of 44,000m².

Several units will incorporate Siemens Gamesa’s GreenerTower, which uses low-emission steel, as well as RecyclableBlade technology to enable the separation and recycling of materials after use.

The turbines will also use RecyclableCoolingLiquid, containing 93% recycled glycol, to further reduce environmental impact.

Siemens Gamesa offshore senior vice president Marc Becker said: “Turning offshore wind ambitions into real projects requires strong partnerships and continued momentum.

“This agreement is an important step, and we look forward to working together to take the project all the way to the finish line.

“With innovations such as GreenerTower and RecyclableBlade, we are ready to bring our technology, experience and sustainability leadership to the project.”

Turbine manufacturing is planned for 2028, with installation scheduled for 2029, subject to a final investment decision (FID).

The overall Zeevonk project, owned by Vattenfall and CIP’s Energy Transition Fund I, will be rolled out in two phases.

Phase II, planned for 2032, intends to add another 1GW of wind and 500MW of system integration capacity.