Eildon is a 135MW hydro power project. It is located on Goulburn river/basin in Victoria, Australia. According to GlobalData, who tracks and profiles over 170,000 power plants worldwide, the project is currently active. It has been developed in a single phase. Post completion of construction, the project got commissioned in 1956. Buy the profile here.

Smarter leaders trust GlobalData

Report-cover

Data Insights Eildon, Australia

Buy the Profile

Data Insights

The gold standard of business intelligence.

Find out more

Description

The project is currently owned by AGL Energy with a stake of 100%.

The hydro reservoir capacity is 3,390 million cubic meter. Eildon underwent through rehabilitation & modernization during 2006. The project generated 184 GWh of electricity.

The hydro power project consists of 2 turbines, each with 7.5MW nameplate capacity.

Development status

The project got commissioned in 1956.

Contractors involved

Andritz Hydro was selected as the turbine supplier for the hydro power project. The company provided 2 turbines, each with 60MW nameplate capacity.

GE Renewable Energy supplied 2 electric generators for the project.

For more details on Eildon, buy the profile here.

This content was updated on 14 October 2024

Data Insights

From

The gold standard of business intelligence.

Blending expert knowledge with cutting-edge technology, GlobalData’s unrivalled proprietary data will enable you to decode what’s happening in your market. You can make better informed decisions and gain a future-proof advantage over your competitors.

GlobalData

GlobalData, the leading provider of industry intelligence, provided the underlying research used to produce this article.

This information is drawn from GlobalData’s Power Intelligence Center, which provides detailed profiles of over 170,000 active, planned and under construction power plants worldwide from announcement through to operation across all technologies and countries worldwide.