Hierro Wind Project is a 41.58MW onshore wind power project. It is located in Castile and León, Spain. According to GlobalData, who tracks and profiles over 170,000 power plants worldwide, the project is currently active. It has been developed in a single phase. Post completion of construction, the project got commissioned in 2019. Buy the profile here.
Description
The project is developed and owned by Naturgy Renovables.
The project generates 148,243MWh electricity thereby offsetting 39,049t of carbon dioxide emissions (CO2) a year.
The project has 114m high towers.
Development status
The project is currently active. The project got commissioned in 2019.
Contractors involved
Siemens Gamesa Renewable Energy was selected as the turbine supplier for the wind power project. The company provided 12 units of G132-3.465 MW turbines, each with 3.465MW nameplate capacity.
For more details on Hierro Wind Project, buy the profile here.
About Naturgy Renovables
Naturgy Renovables SL (Naturgy Renovables) generates, transmits, and distributes electricity through solar energy. Naturgy Renovables headquartered in Spain.
Data Insights
From
The gold standard of business intelligence.
Blending expert knowledge with cutting-edge technology, GlobalData’s unrivalled proprietary data will enable you to decode what’s happening in your market. You can make better informed decisions and gain a future-proof advantage over your competitors.