Aboisso is a 90MW hydro power project. It is planned on Comoe river/basin in Lagunes, Ivory Coast. The project is currently in announced stage. It will be developed in single phase. The project construction is likely to commence in 2024 and is expected to enter into commercial operation in 2026.

Project Type Total Capacity (MW) Active Capacity (MW) Pipeline Capacity (MW) Project Status Project Location Project Developer
Hydropower 90 90 Announced Lagunes, Ivory Coast

Description

The project is currently owned by Ministere du Petrole de l’energie et du Developpement des Energies Renouvelables.

The project is expected to generate 392 GWh of electricity. The project cost is expected to be around $446.657m.

Development Status

The project construction is expected to commence from 2024. Subsequent to that it will enter into commercial operation by 2026.

GlobalData Strategic Intelligence

US Tariffs are shifting - will you react or anticipate?

Don’t let policy changes catch you off guard. Stay proactive with real-time data and expert analysis.

By GlobalData

Methodology

All power projects included in this report are drawn from GlobalData’s Power Intelligence Center. The information regarding the project parameters is sourced through secondary information sources such as electric utilities, equipment manufacturers, developers, project proponent’s – news, deals and financial reporting, regulatory body, associations, government planning reports and publications. Wherever needed the information is further validated through primary from various stakeholders across the power value chain and professionals from leading players within the power sector.