Agua Prieta is a 240MW hydro power project. It is located on Rio Grande de Santiago river/basin in Jalisco, Mexico. The project is currently active. It has been developed in single phase. Post completion of construction, the project got commissioned in 1993.
Project Type | Total Capacity (MW) | Active Capacity (MW) | Pipeline Capacity (MW) | Project Status | Project Location | Project Developer | Hydropower | 240 | 240 | – | Active | Jalisco, Mexico |
---|
Description
The project is currently owned by Comision Federal de Electricidad.
The gross head of the project is 518m. The project generated 242.91 GWh of electricity.
Development Status
The project got commissioned in 1993.

US Tariffs are shifting - will you react or anticipate?
Don’t let policy changes catch you off guard. Stay proactive with real-time data and expert analysis.
By GlobalDataContractors Involved
Andritz Hydro was selected as the turbine supplier for the hydro power project. The company provided 2 units of pelton turbines, each with 120MW nameplate capacity.
Toshiba Energy Systems and Solutions supplied 2 electric generators for the project.
Methodology
All power projects included in this report are drawn from GlobalData’s Power Intelligence Center. The information regarding the project parameters is sourced through secondary information sources such as electric utilities, equipment manufacturers, developers, project proponent’s – news, deals and financial reporting, regulatory body, associations, government planning reports and publications. Wherever needed the information is further validated through primary from various stakeholders across the power value chain and professionals from leading players within the power sector.