Azumi is a 623MW hydro power project. It is located on Azusagawa, Midonogawa river/basin in Nagano, Japan. The project is currently active. It has been developed in single phase. The project construction commenced in 1961 and subsequently entered into commercial operation in 1969.

Project Type Total Capacity (MW) Active Capacity (MW) Pipeline Capacity (MW) Project Status Project Location Project Developer
Hydropower 623 623 Active Nagano, Japan

Description

The project is currently owned by Tokyo Electric Power Co Holdings.

Azumi is a pumped storage project. The hydro reservoir capacity is 123 million cubic meter. The net head of the project is 135.78m. Azumi underwent through rehabilitation & modernization during 2003.

The project has 6 electric generators installed at the site.

Development Status

The project construction commenced in 1961 and subsequently entered into commercial operation in 1969.

Contractors Involved

Toshiba Energy Systems and Solutions was selected as the turbine supplier for the hydro power project. The company provided 4 units of francis turbines, each with 103MW nameplate capacity.

Toshiba Energy Systems and Solutions was selected as the turbine supplier for the hydro power project. The company provided 2 units of francis turbines, each with 106MW nameplate capacity.

Methodology

All power projects included in this report are drawn from GlobalData’s Power Intelligence Center. The information regarding the project parameters is sourced through secondary information sources such as electric utilities, equipment manufacturers, developers, project proponent’s – news, deals and financial reporting, regulatory body, associations, government planning reports and publications. Wherever needed the information is further validated through primary from various stakeholders across the power value chain and professionals from leading players within the power sector.