Ba Thuoc 1 is a 60MW hydro power project. It is located on Ma river/basin in Thanh Hoa, Vietnam. The project is currently active. It has been developed in single phase. The project construction commenced in 2013 and subsequently entered into commercial operation in 2017.

Project Type Total Capacity (MW) Active Capacity (MW) Pipeline Capacity (MW) Project Status Project Location Project Developer
Hydropower 60 60 Active Thanh Hoa, Vietnam Hoang Anh Thanh Hoa Hydroelectric Joint Stock

Description

The project is developed and owned by Hoang Anh Thanh Hoa Hydroelectric Joint Stock.

Ba Thuoc 1 is a run-of-river project. The project generated 216.04 GWh of electricity.

The hydro power project consists of 4 turbines, each with 15.464MW nameplate capacity.

The project has 4 electric generators installed at the site. The generator capacity is 16.67 MVA.

Development Status

The project construction commenced in 2013 and subsequently entered into commercial operation in 2017.

Methodology

All power projects included in this report are drawn from GlobalData’s Power Intelligence Center. The information regarding the project parameters is sourced through secondary information sources such as electric utilities, equipment manufacturers, developers, project proponent’s – news, deals and financial reporting, regulatory body, associations, government planning reports and publications. Wherever needed the information is further validated through primary from various stakeholders across the power value chain and professionals from leading players within the power sector.