Banias Power Station Extension is a 300MW gas fired power project. It is located in Tartus, Syria. The project is currently active. It has been developed in single phase. Post completion of construction, the project got commissioned in 2010.

Project Type Total Capacity (MW) Active Capacity (MW) Pipeline Capacity (MW) Project Status Project Location Project Developer
Thermal 300 300 Active Tartus, Syria

Description

The project is currently owned by Public Establishment for Electricity Generation and Transmission with a stake of 100%.

It is a Gas Turbine power plant. The power plant run on dual-fuel. The primary fuel being used to power the plant is natural gas. In case of shortage of natural gas the plant can also run on Distillate Oil.

The project cost is $302.25m.

The Gas fired project consists of 2 gas turbines, each with 150MW nameplate capacity.

Development Status

The project got commissioned in 2010.

Methodology

All power projects included in this report are drawn from GlobalData’s Power Intelligence Center. The information regarding the project parameters is sourced through secondary information sources such as electric utilities, equipment manufacturers, developers, project proponent’s – news, deals and financial reporting, regulatory body, associations, government planning reports and publications. Wherever needed the information is further validated through primary from various stakeholders across the power value chain and professionals from leading players within the power sector.