Barh – Gorakhpur Line is a 400kV overhead line with a length of 698km from Barh, Bihar, India, to Gorakhpur, Uttar Pradesh, India.
Construction works on the Barh – Gorakhpur Line started in 2014 and the project was commissioned in 2015.
Description
The Barh – Gorakhpur Line, which is an overhead line, is being operated by Darbhanga-Motihari Transmission. The Barh – Gorakhpur Line is a new line. The line carries alternating current (AC) through double circuit cable.
Barh – Gorakhpur Line project development status
The development of the Barh – Gorakhpur Line project was approved by Bihar Electricity Regulatory Commission in 2014 and the project works were completed in 2015.

US Tariffs are shifting - will you react or anticipate?
Don’t let policy changes catch you off guard. Stay proactive with real-time data and expert analysis.
By GlobalDataMethodology
All publicly-announced T&D Line & Substation projects included in this analysis are drawn from GlobalData’s Power IC. The information regarding the projects is sourced through secondary information sources such as country specific utility players, company news and reports, statistical organisations, regulatory body, government planning reports and their publications and is further validated through primary from various stakeholders such as power utility companies, consultants, energy associations of respective countries, government bodies and professionals from leading players in the power sector.