Barra Dos Coqueiros is a 34.5MW onshore wind power project. It is located in Sergipe, Brazil. The project is currently active. It has been developed in single phase. Post completion of construction, the project got commissioned in 2012.

Project Type Total Capacity (MW) Active Capacity (MW) Pipeline Capacity (MW) Project Status Project Location Project Developer
Onshore 34.5 34.5 Active Sergipe, Brazil Desenvix Energias Renovaveis

Description

The project was developed by Desenvix Energias Renovaveis and is currently owned by Statkraft with a stake of 88%.

The project cost is $90.494m.

Development Status

The project is currently active. The project got commissioned in 2012.

GlobalData Strategic Intelligence

US Tariffs are shifting - will you react or anticipate?

Don’t let policy changes catch you off guard. Stay proactive with real-time data and expert analysis.

By GlobalData

Power Purchase Agreement

The power generated from the project is sold to Camara de Comercializacao de Energia Eletrica under a power purchase agreement for a period of 20 years.

Contractors Involved

Engevix Engenharia e Projetos was selected to render EPC services for the wind power project.

Sinovel Wind Group was selected as the turbine supplier for the wind power project. The company provided 23 units of SL1500/82 turbines, each with 1.5MW nameplate capacity.

Methodology

All power projects included in this report are drawn from GlobalData’s Power Intelligence Center. The information regarding the project parameters is sourced through secondary information sources such as electric utilities, equipment manufacturers, developers, project proponent’s – news, deals and financial reporting, regulatory body, associations, government planning reports and publications. Wherever needed the information is further validated through primary from various stakeholders across the power value chain and professionals from leading players within the power sector.