Bland – Franks Line is a 345kV overhead line with a length of 70.8km from Bland, Missouri, US, to Franks, Missouri, US.
The project, which is currently in the planning stage, is expected to be commissioned in 2024.
Description
Bland – Franks Line is an overhead line that will be operated by Ameren Missouri. The line will carry alternating current (AC) through triple circuit cable.
Approximately $21.7m was financed by the authorities to undertake the construction works of the project.
Bland – Franks Line project development status

US Tariffs are shifting - will you react or anticipate?
Don’t let policy changes catch you off guard. Stay proactive with real-time data and expert analysis.
By GlobalDataThe construction works on the Bland – Franks Line project will be commenced in 2023 and commissioning is expected in 2024.
About Ameren Missouri
Ameren Missouri (Ameren Missouri) that designs and builds regional transmission projects. The company is headquartered in St. Louis, Missouri, United States.
Methodology
All publicly-announced T&D Line & Substation projects included in this analysis are drawn from GlobalData’s Power IC. The information regarding the projects is sourced through secondary information sources such as country specific utility players, company news and reports, statistical organisations, regulatory body, government planning reports and their publications and is further validated through primary from various stakeholders such as power utility companies, consultants, energy associations of respective countries, government bodies and professionals from leading players in the power sector.