Blowering is an 80MW hydro power project. It is located on Tumut river/basin in New South Wales, Australia. The project is currently active. It has been developed in single phase. The project construction commenced in 1964 and subsequently entered into commercial operation in 1968.
Project Type | Total Capacity (MW) | Active Capacity (MW) | Pipeline Capacity (MW) | Project Status | Project Location | Project Developer | Hydropower | 80 | 80 | – | Active | New South Wales, Australia |
---|
Description
The project is currently owned by Snowy Hydro with a stake of 100%.
Blowering is a reservoir based project. The hydro reservoir capacity is 1,632.4 million cubic meter. The net head of the project is 86.6m. Blowering underwent through rehabilitation & modernization during 2010.
The hydro power project consists of 1 turbine with 80MW nameplate capacity.
Development Status
The project construction commenced in 1964 and subsequently entered into commercial operation in 1968.
Methodology
All power projects included in this report are drawn from GlobalData’s Power Intelligence Center. The information regarding the project parameters is sourced through secondary information sources such as electric utilities, equipment manufacturers, developers, project proponent’s – news, deals and financial reporting, regulatory body, associations, government planning reports and publications. Wherever needed the information is further validated through primary from various stakeholders across the power value chain and professionals from leading players within the power sector.