Canoas is a 31.5MW onshore wind power project. It is located in Paraiba, Brazil. The project is currently active. It has been developed in single phase. Post completion of construction, the project got commissioned in September 2017.

Project Type Total Capacity (MW) Active Capacity (MW) Pipeline Capacity (MW) Project Status Project Location Project Developer
Onshore 31.5 31.5 Active Paraiba, Brazil Forca Eolica do Brasil

Description

The project was developed by Forca Eolica do Brasil and is currently owned by Iberdrola with a stake of 100%.

The project cost is $54.653m.

Development Status

The project is currently active. The project got commissioned in September 2017.

Contractors Involved

Siemens Gamesa Renewable Energy was selected as the turbine supplier for the wind power project. The company provided 15 units of G114-2.1 MW turbines, each with 2.1MW nameplate capacity.

Siemens Gamesa Renewable Energy is the O&M contractor for the wind power project.

Methodology

All power projects included in this report are drawn from GlobalData’s Power Intelligence Center. The information regarding the project parameters is sourced through secondary information sources such as electric utilities, equipment manufacturers, developers, project proponent’s – news, deals and financial reporting, regulatory body, associations, government planning reports and publications. Wherever needed the information is further validated through primary from various stakeholders across the power value chain and professionals from leading players within the power sector.