Catalan is a 169MW hydro power project. It is located on Seyhan river/basin in Adana, Turkey. The project is currently active. It has been developed in single phase. The project construction commenced in 1982 and subsequently entered into commercial operation in 1997.
| Project Type | Total Capacity (MW) | Active Capacity (MW) | Pipeline Capacity (MW) | Project Status | Project Location | Project Developer | Hydropower | 169 | 169 | – | Active | Adana, Turkey |
|---|
Description
Discover B2B Marketing That Performs
Combine business intelligence and editorial excellence to reach engaged professionals across 36 leading media platforms.
The project is currently owned by Devlet su Isleri Genel Mudurlugu.
The project generated 596 GWh of electricity.
The hydro power project consists of 3 turbines, each with 56.3MW nameplate capacity.
The project has 3 electric generators installed at the site. The generator capacity is 65 MVA.
US Tariffs are shifting - will you react or anticipate?
Don’t let policy changes catch you off guard. Stay proactive with real-time data and expert analysis.
By GlobalDataDevelopment Status
The project construction commenced in 1982 and subsequently entered into commercial operation in 1997.
Methodology
All power projects included in this report are drawn from GlobalData’s Power Intelligence Center. The information regarding the project parameters is sourced through secondary information sources such as electric utilities, equipment manufacturers, developers, project proponent’s – news, deals and financial reporting, regulatory body, associations, government planning reports and publications. Wherever needed the information is further validated through primary from various stakeholders across the power value chain and professionals from leading players within the power sector.