Charanka -Phase I -SunEdison LLC Solar Park (Gujarat Solar Policy – Phase II) is a 25MW solar PV power project. It is located in Gujarat, India. The project is currently active. It has been developed in single phase. Post completion of construction, the project got commissioned in January 2012.
Project Type | Total Capacity (MW) | Active Capacity (MW) | Pipeline Capacity (MW) | Project Status | Project Location | Project Developer | Solar PV | 25 | 25 | – | Active | Gujarat, India | SunEdison Energy India |
---|
Description
The project is developed and owned by SunEdison Energy India.
Charanka -Phase I -SunEdison LLC Solar Park (Gujarat Solar Policy – Phase II) is a ground-mounted solar project.
The project generates 42,517.67MWh of electricity. The project cost is $68.251m.
Development Status
The project got commissioned in January 2012.
Power Purchase Agreement
The power generated from the project is sold to Gujarat Urja Vikas Nigam under a power purchase agreement for a period of 25 years. The contracted capacity is 25MW.
Contractors Involved
Larsen & Toubro (Oman) was selected to render EPC services for the solar PV power project.
The solar PV modules for the project were supplied by Trina Solar and Zhejiang Chint New Energy Development.
Methodology
All power projects included in this report are drawn from GlobalData’s Power Intelligence Center. The information regarding the project parameters is sourced through secondary information sources such as electric utilities, equipment manufacturers, developers, project proponent’s – news, deals and financial reporting, regulatory body, associations, government planning reports and publications. Wherever needed the information is further validated through primary from various stakeholders across the power value chain and professionals from leading players within the power sector.