Chelyabinsk Cogeneration Plant 3 is a 360MW gas fired power project. It is located in Chelyabinsk, Russia. The project is currently active. It has been developed in multiple phases. Post completion of construction, the project got commissioned in April 1996.

Project Type Total Capacity (MW) Active Capacity (MW) Pipeline Capacity (MW) Project Status Project Location Project Developer
Thermal 360 360 Active Chelyabinsk, Russia

Description

The project is currently owned by Fortum with a stake of 100%.

It is a Steam Turbine with Cogen power plant.

Development Status

The project got commissioned in April 1996.

Contractors Involved

Chelyabinsk Cogeneration Plant 3 (Chelyabinsk Cogeneration Plant 3 Unit I) is equipped with Leningradsky Metallichesky Zavod T-180-130 steam turbine. The phase consists of 1 steam turbine with 180MW nameplate capacity.

Chelyabinsk Cogeneration Plant 3 (Chelyabinsk Cogeneration Plant 3 Unit II) is equipped with Power Machines steam turbine. The phase consists of 1 steam turbine with 180MW nameplate capacity.

Electrosila supplied electric generator for the Chelyabinsk Cogeneration Plant 3 (Chelyabinsk Cogeneration Plant 3 Unit I).

Taganrog Boiler-Making Works Krasny Kotelshchik supplied steam boiler for the Chelyabinsk Cogeneration Plant 3 (Chelyabinsk Cogeneration Plant 3 Unit II).

Methodology

All power projects included in this report are drawn from GlobalData’s Power Intelligence Center. The information regarding the project parameters is sourced through secondary information sources such as electric utilities, equipment manufacturers, developers, project proponent’s – news, deals and financial reporting, regulatory body, associations, government planning reports and publications. Wherever needed the information is further validated through primary from various stakeholders across the power value chain and professionals from leading players within the power sector.