Chernobyl Solar PV Park is a 1,224MW solar PV power project. It is planned in Kiev, Ukraine. The project is currently in permitting stage. It will be developed in single phase. Post completion of the construction, the project is expected to get commissioned in 2023.

Project Type Total Capacity (MW) Active Capacity (MW) Pipeline Capacity (MW) Project Status Project Location Project Developer
Solar PV 1,224 1,224 Permitting Kiev, Ukraine

Description

Chernobyl Solar PV Park is a ground-mounted solar project which is planned over 2,000 hectares.

The project is expected to generate 1,200,000MWh of electricity. The project cost is expected to be around $1,300m.

The solar power project consists of modules with rated capacity of 335W.

Development Status

GlobalData Strategic Intelligence

US Tariffs are shifting - will you react or anticipate?

Don’t let policy changes catch you off guard. Stay proactive with real-time data and expert analysis.

By GlobalData

Post completion of the construction, the project is expected to get commissioned in 2023.

Methodology

All power projects included in this report are drawn from GlobalData’s Power Intelligence Center. The information regarding the project parameters is sourced through secondary information sources such as electric utilities, equipment manufacturers, developers, project proponent’s – news, deals and financial reporting, regulatory body, associations, government planning reports and publications. Wherever needed the information is further validated through primary from various stakeholders across the power value chain and professionals from leading players within the power sector.