Chihuahua II (El Encino) Combined Cycle Power Plant, Mexico

By Carmen

Chihuahua II (El Encino) Combined Cycle Power Plant is a 619MW gas fired power project. It is located in Chihuahua, Mexico. The project is currently active. It has been developed in multiple phases. Post completion of construction, the project got commissioned in May 2001.

Project Type Total Capacity (MW) Active Capacity (MW) Pipeline Capacity (MW) Project Status Project Location Project Developer
Thermal 619 619 Active Chihuahua, Mexico

Description

The project is currently owned by Comision Federal de Electricidad with a stake of 100%.

It is a Combined Cycle Gas Turbine (CCGT) power plant.

The project generated 4,597,000MWh of electricity.

Chihuahua II (El Encino) Combined Cycle Power Plant (Chihuahua II CCGT Power Plant Phase II) consists of 1 steam turbine with 64.9MW nameplate capacity.

Content from our partners
How Hengst helped to keep Germany’s charity “star singers” shining
How one power station prevented frequent shutdowns with three-stage air filtration
Reimagining the carbon problem

Development Status

The project got commissioned in May 2001.

Power Purchase Agreement

The power generated from the project is sold to Comision Federal de Electricidad under a power purchase agreement with a contracted capacity is 619MW.

Contractors Involved

Cobra Gestion de Infraestructuras, Dragados Industrial and Initec Energia were selected to render EPC services for the Chihuahua II (El Encino) Combined Cycle Power Plant (Chihuahua II CCGT Power Plant Phase II).

Chihuahua II (El Encino) Combined Cycle Power Plant (Chihuahua II CCGT Power Plant Phase I) is equipped with Mitsubishi Power gas turbines. The phase consists of 2 gas turbines, each with 138.15MW nameplate capacity.

Chihuahua II (El Encino) Combined Cycle Power Plant (Chihuahua II CCGT Power Plant Phase I) is equipped with Mitsubishi Power steam turbine. The phase consists of 1 steam turbine with 147MW nameplate capacity.

Chihuahua II (El Encino) Combined Cycle Power Plant (Chihuahua II CCGT Power Plant Phase II) is equipped with Siemens Energy gas turbine. The phase consists of 1 gas turbine with 130.8MW nameplate capacity.

Mitsubishi Power supplied electric generator for the Chihuahua II (El Encino) Combined Cycle Power Plant (Chihuahua II CCGT Power Plant Phase I).

Siemens Energy supplied electric generator for the Chihuahua II (El Encino) Combined Cycle Power Plant (Chihuahua II CCGT Power Plant Phase II).

Cerrey supplied steam boiler for the project.

Methodology

All power projects included in this report are drawn from GlobalData’s Power Intelligence Center. The information regarding the project parameters is sourced through secondary information sources such as electric utilities, equipment manufacturers, developers, project proponent’s – news, deals and financial reporting, regulatory body, associations, government planning reports and publications. Wherever needed the information is further validated through primary from various stakeholders across the power value chain and professionals from leading players within the power sector.

Related Companies

NEWSLETTER Sign up Tick the boxes of the newsletters you would like to receive. The top stories of the day delivered to you every weekday. A weekly roundup of the latest news and analysis, sent every Wednesday. The power industry's most comprehensive news and information delivered every month.
I consent to GlobalData UK Limited collecting my details provided via this form in accordance with the Privacy Policy
SUBSCRIBED

THANK YOU