Churchill Falls is a 5,428MW hydro power project. It is located on Churchill river/basin in Newfoundland and Labrador, Canada. The project is currently active. It has been developed in single phase. The project construction commenced in 1967 and subsequently entered into commercial operation in 1971.

Project Type Total Capacity (MW) Active Capacity (MW) Pipeline Capacity (MW) Project Status Project Location Project Developer
Hydropower 5,428 5,428 Active Newfoundland and Labrador, Canada

Description

Nalcor Energy and Hydro-Quebec are currently owning the project having ownership stake of 65.8% and 34.2% respectively.

Churchill Falls is a reservoir based project. The hydro reservoir capacity is 32,320 million cubic meter. The net head of the project is 312.4m. The total number of penstocks, pipes or long channels that carry water down from the hydroelectric reservoir to the turbines inside the actual power station, are 11 in number. The penstock length is 426.72m. The penstock diameter is 4.48m. The project generated 35,000 GWh of electricity.

The hydro power project consists of 6 turbines.

The project has 6 electric generators installed at the site. The generator capacity is 50 MVA.

Content from our partners
Green investment: What gives Scotland multiple advantages
How Hengst helped to keep Germany’s charity “star singers” shining
How one power station prevented frequent shutdowns with three-stage air filtration

Development Status

The project construction commenced in 1967 and subsequently entered into commercial operation in 1971.

Power Purchase Agreement

The power generated from the Churchill Falls is sold to Hydro-Quebec under a power purchase agreement. The power is sold at the rate of $0.002kWh for a period of 65.00 years, starting from 1971.

Contractors Involved

Andritz Hydro was selected as the turbine supplier for the hydro power project. The company provided 5 units of francis turbines.

Andritz Hydro supplied 5 electric generators for the project. The generator capacity is 50 MVA.

Methodology

All power projects included in this report are drawn from GlobalData’s Power Intelligence Center. The information regarding the project parameters is sourced through secondary information sources such as electric utilities, equipment manufacturers, developers, project proponent’s – news, deals and financial reporting, regulatory body, associations, government planning reports and publications. Wherever needed the information is further validated through primary from various stakeholders across the power value chain and professionals from leading players within the power sector.

Related Companies

NEWSLETTER Sign up Tick the boxes of the newsletters you would like to receive. The top stories of the day delivered to you every weekday. A weekly roundup of the latest news and analysis, sent every Wednesday. The power industry's most comprehensive news and information delivered every month.
I consent to GlobalData UK Limited collecting my details provided via this form in accordance with the Privacy Policy
SUBSCRIBED

THANK YOU