Cimarron Bend Wind Farm, US

By Carmen

Cimarron Bend Wind Farm is a 599MW onshore wind power project. It is located in Kansas, the US. The project is currently active. It has been developed in multiple phases. Post completion of construction, the project got commissioned in December 2016.

Project Type Total Capacity (MW) Active Capacity (MW) Pipeline Capacity (MW) Project Status Project Location Project Developer
Onshore 599 599 Active Kansas, the US Cimarron Bend Wind Project I; Cimarron Bend Wind Project II; Cimarron Bend Wind Project III

Description

The project is developed by Cimarron Bend Wind Project I, Cimarron Bend Wind Project II and Cimarron Bend Wind Project III. These companies also have ownership stakes in the project.

The project generates 2,700GWh electricity and supplies enough clean energy to power 180,000 households, offsetting 1,700,000t of carbon dioxide emissions (CO2) a year.

Cimarron Bend Wind Farm (Cimarron Bend III) consists of 74 turbines.

Development Status

Content from our partners
How Hengst helped to keep Germany’s charity “star singers” shining
How one power station prevented frequent shutdowns with three-stage air filtration
Reimagining the carbon problem

The project is currently active. The project got commissioned in December 2016.

Power Purchase Agreement

Evergy, Google Energy, Kansas City Board of Public Utilities and Missouri Public Utility Alliance are the power offtakers from the project.

Contractors Involved

Cimarron Bend Wind Farm (Cimarron Bend I) is equipped with Vestas Wind Systems V110-2.0 MW turbines. The phase consists of 100 turbines with 2MW nameplate capacity.

Cimarron Bend Wind Farm (Cimarron Bend II) is equipped with Vestas Wind Systems V110-2.0 MW turbines. The phase consists of 100 turbines with 2MW nameplate capacity.

Methodology

All power projects included in this report are drawn from GlobalData’s Power Intelligence Center. The information regarding the project parameters is sourced through secondary information sources such as electric utilities, equipment manufacturers, developers, project proponent’s – news, deals and financial reporting, regulatory body, associations, government planning reports and publications. Wherever needed the information is further validated through primary from various stakeholders across the power value chain and professionals from leading players within the power sector.

Related Companies

NEWSLETTER Sign up Tick the boxes of the newsletters you would like to receive. The top stories of the day delivered to you every weekday. A weekly roundup of the latest news and analysis, sent every Wednesday. The power industry's most comprehensive news and information delivered every month.
I consent to GlobalData UK Limited collecting my details provided via this form in accordance with the Privacy Policy
SUBSCRIBED

THANK YOU