CPI Ningxia Power Generation Zaoquan Power Plant is a 1,320MW coal fired power project. It is located in Ningxia, China. The project is currently active. It has been developed in multiple phases. Post completion of construction, the project got commissioned in November 2017.
Project Type | Total Capacity (MW) | Active Capacity (MW) | Pipeline Capacity (MW) | Project Status | Project Location | Project Developer | Thermal | 1,320 | 1,320 | – | Active | Ningxia, China | China Power Investment; Zhejiang Energy Group |
---|
Description
The project was developed by China Power Investment and Zhejiang Energy Group. Zhejiang Energy Group and State Power Investment are currently owning the project having ownership stake of 51% and 49% respectively.
It is a steam turbine power plant. The fuel is procured from Majiatan Yuanyanghu Mines.
Development Status
The project got commissioned in November 2017.
About China Power Investment
State Power Investment Corp Ltd (SPIC), established by the merger of China Power Investment Corp and State Nuclear Power Technology Corp, is a state-owned power generator enterprise. The company owns and operates power generation plants and offers hydro-power, thermal power, nuclear power and new energy generation services. The company carries out research and development, designing, and manufacturing of nuclear power components and equipment. SPIC’s business activities include project contracting, mining investments, life cycle services and technical supports. The company operates in China, Japan, Malta, Australia, India, Turkey, Pakistan, Brazil and Myanmar. SPIC is headquartered in Beijing, China.
Methodology
All power projects included in this report are drawn from GlobalData’s Power Intelligence Center. The information regarding the project parameters is sourced through secondary information sources such as electric utilities, equipment manufacturers, developers, project proponent’s – news, deals and financial reporting, regulatory body, associations, government planning reports and publications. Wherever needed the information is further validated through primary from various stakeholders across the power value chain and professionals from leading players within the power sector.