Dalesice is a 480MW hydro power project. It is located on Jihlava river/basin in Vysocina, Czech Republic. The project is currently active. It has been developed in single phase. The project construction commenced in 1970 and subsequently entered into commercial operation in 1978.
Project Type | Total Capacity (MW) | Active Capacity (MW) | Pipeline Capacity (MW) | Project Status | Project Location | Project Developer | Hydropower | 480 | 480 | – | Active | Vysocina, Czech Republic |
---|
Description
The project is currently owned by CEZ.
Dalesice is a pumped storage project. The hydro reservoir capacity is 127.3 million cubic meter. The gross head of the project is 90m. Dalesice underwent through rehabilitation & modernization during 2008. The project generated 10.556 GWh of electricity.
Development Status
The project construction commenced in 1970 and subsequently entered into commercial operation in 1978.
Contractors Involved
CKD Blansko Holding was selected as the turbine supplier for the hydro power project. The company provided 4 units of francis turbines, each with 112.5MW nameplate capacity.
Methodology
All power projects included in this report are drawn from GlobalData’s Power Intelligence Center. The information regarding the project parameters is sourced through secondary information sources such as electric utilities, equipment manufacturers, developers, project proponent’s – news, deals and financial reporting, regulatory body, associations, government planning reports and publications. Wherever needed the information is further validated through primary from various stakeholders across the power value chain and professionals from leading players within the power sector.