Domtar Mill Biomass Power Plant is a 50MW biopower project. It is located in Wisconsin, the US. The project is currently active. It has been developed in single phase. Post completion of construction, the project got commissioned in November 2013.

Project Type Total Capacity (MW) Active Capacity (MW) Pipeline Capacity (MW) Project Status Project Location Project Developer
Biopower 50 50 Active Wisconsin, the US

Description

The project is currently owned by We Energies.

The project supplies enough clean energy to power 40,000 households. The project cost is $250m.

Domtar Mill Biomass Power Plant is a combined heat and power (CHP) project. Wood waste which is a kind of wood by-product is used as a feedstock to power the project.

Development Status

GlobalData Strategic Intelligence

US Tariffs are shifting - will you react or anticipate?

Don’t let policy changes catch you off guard. Stay proactive with real-time data and expert analysis.

By GlobalData

The project got commissioned in November 2013.

Contractors Involved

General Electric was selected as the steam turbine supplier for the project.

Neles supplied steam boiler for the project.

Methodology

All power projects included in this report are drawn from GlobalData’s Power Intelligence Center. The information regarding the project parameters is sourced through secondary information sources such as electric utilities, equipment manufacturers, developers, project proponent’s – news, deals and financial reporting, regulatory body, associations, government planning reports and publications. Wherever needed the information is further validated through primary from various stakeholders across the power value chain and professionals from leading players within the power sector.