EGA – Al Taweelah Combined Cycle Power Plant, United Arab Emirates

By Carmen

EGA – Al Taweelah Combined Cycle Power Plant is a 2,620MW gas fired power project. It is located in Abu Dhabi, United Arab Emirates. The project is currently active. It has been developed in multiple phases. Post completion of construction, the project got commissioned in 2010.

Project Type Total Capacity (MW) Active Capacity (MW) Pipeline Capacity (MW) Project Status Project Location Project Developer
Thermal 2,620 2,620 Active Abu Dhabi, United Arab Emirates

Description

The project is currently owned by Emirates Global Aluminium with a stake of 100%.

It is a combined cycle gas turbine (ccgt) power plant. The power plant run on dual-fuel. The primary fuel being used to power the plant is natural gas. In case of shortage of natural gas the plant can also run on Distillate Fuel Oil.

Development Status

The project got commissioned in 2010.

Contractors Involved

Samsung C&T was selected to render EPC services for the EGA – Al Taweelah Combined Cycle Power Plant (EGA – Al Taweelah Combined Cycle Power Plant Block III) project. Samsung C&T was selected to render EPC services for the EGA – Al Taweelah Combined Cycle Power Plant (EGA – Al Taweelah Combined Cycle Power Plant Block IV) project.

EGA – Al Taweelah Combined Cycle Power Plant (EGA – Al Taweelah Combined Cycle Power Plant Block I) is equipped with GE Power 9F.03 gas turbines. The phase consists of 2 gas turbines with 218MW nameplate capacity.

EGA – Al Taweelah Combined Cycle Power Plant (EGA – Al Taweelah Combined Cycle Power Plant Block I) is equipped with GE Power GE-C7 steam turbine. The phase consists of 1 steam turbine with 219MW nameplate capacity.

EGA – Al Taweelah Combined Cycle Power Plant (EGA – Al Taweelah Combined Cycle Power Plant Block II) is equipped with GE Power 9F.03 gas turbines. The phase consists of 2 gas turbines with 218MW nameplate capacity.

EGA – Al Taweelah Combined Cycle Power Plant (EGA – Al Taweelah Combined Cycle Power Plant Block II) is equipped with GE Power GE-C7 steam turbine. The phase consists of 1 steam turbine with 219MW nameplate capacity.

EGA – Al Taweelah Combined Cycle Power Plant (EGA – Al Taweelah Combined Cycle Power Plant Block III) is equipped with GE Power 9F.03 gas turbines. The phase consists of 2 gas turbines with 218MW nameplate capacity.

EGA – Al Taweelah Combined Cycle Power Plant (EGA – Al Taweelah Combined Cycle Power Plant Block III) is equipped with GE Power C5 steam turbine. The phase consists of 1 steam turbine with 219MW nameplate capacity.

EGA – Al Taweelah Combined Cycle Power Plant (EGA – Al Taweelah Combined Cycle Power Plant Block IV) is equipped with GE Power 9F.03 gas turbines. The phase consists of 2 gas turbines with 218MW nameplate capacity.

EGA – Al Taweelah Combined Cycle Power Plant (EGA – Al Taweelah Combined Cycle Power Plant Block IV) is equipped with GE Power C5 steam turbine. The phase consists of 1 steam turbine with 219MW nameplate capacity.

GE Power supplied electric generator for the EGA – Al Taweelah Combined Cycle Power Plant (EGA – Al Taweelah Combined Cycle Power Plant Block I).

GE Power supplied electric generator for the EGA – Al Taweelah Combined Cycle Power Plant (EGA – Al Taweelah Combined Cycle Power Plant Block II).

GE Power supplied electric generator for the EGA – Al Taweelah Combined Cycle Power Plant (EGA – Al Taweelah Combined Cycle Power Plant Block III).

GE Power supplied electric generator for the EGA – Al Taweelah Combined Cycle Power Plant (EGA – Al Taweelah Combined Cycle Power Plant Block IV).

Doosan Heavy Industries Vietnam supplied steam boiler for the EGA – Al Taweelah Combined Cycle Power Plant (EGA – Al Taweelah Combined Cycle Power Plant Block I).

Doosan Heavy Industries Vietnam supplied steam boiler for the EGA – Al Taweelah Combined Cycle Power Plant (EGA – Al Taweelah Combined Cycle Power Plant Block II).

BHI supplied steam boiler for the EGA – Al Taweelah Combined Cycle Power Plant (EGA – Al Taweelah Combined Cycle Power Plant Block III).

BHI supplied steam boiler for the EGA – Al Taweelah Combined Cycle Power Plant (EGA – Al Taweelah Combined Cycle Power Plant Block IV).

Methodology

All power projects included in this report are drawn from GlobalData’s Power Intelligence Center. The information regarding the project parameters is sourced through secondary information sources such as electric utilities, equipment manufacturers, developers, project proponent’s – news, deals and financial reporting, regulatory body, associations, government planning reports and publications. Wherever needed the information is further validated through primary from various stakeholders across the power value chain and professionals from leading players within the power sector.

Related Companies

NEWSLETTER Sign up Tick the boxes of the newsletters you would like to receive. The top stories of the day delivered to you every weekday. A weekly roundup of the latest news and analysis, sent every Wednesday. The power industry's most comprehensive news and information delivered every month.
I consent to GlobalData UK Limited collecting my details provided via this form in accordance with the Privacy Policy
SUBSCRIBED

THANK YOU

Thank you for subscribing to Power Technology