El Sauz Combined Cycle Power Plant is a 601MW gas fired power project. It is located in Queretaro, Mexico. According to GlobalData, who tracks and profiles over 170,000 power plants worldwide, the project is currently active. It has been developed in multiple phases. Post completion of construction, the project got commissioned in July 1981. Buy the profile here.
Description
The project is currently owned by Comision Federal de Electricidad with a stake of 100%.
It is a Combined Cycle Gas Turbine (CCGT) power plant that is used for Baseload.
The project generated 4,167,000MWh of electricity.
Development status
The project got commissioned in July 1981.
Power purchase agreement
The power generated from the project is sold to Comision Federal de Electricidad under a power purchase agreement with a contracted capacity is 591MW.
See Also:
Contractors involved
The Gas fired project have been supplied by GE Power and Siemens Energy.
The electric generators for the project were procured from GE Power and Siemens Energy.
Cerrey supplied steam boiler for the project.
Cerrey supplied steam boiler for the project.
Cerrey supplied steam boiler for the project.
For more details on El Sauz Combined Cycle Power Plant, buy the profile here.
Premium Insights
From
The gold standard of business intelligence.
Blending expert knowledge with cutting-edge technology, GlobalData’s unrivalled proprietary data will enable you to decode what’s happening in your market. You can make better informed decisions and gain a future-proof advantage over your competitors.