Forney Energy Center is a 1,894.2MW gas fired power project. It is located in Texas, the US. According to GlobalData, who tracks and profiles over 170,000 power plants worldwide, the project is currently active. It has been developed in multiple phases. Post completion of construction, the project got commissioned in February 2003. Buy the profile here.

Smarter leaders trust GlobalData

Report-cover

Premium Insights Forney Energy Center

Buy the Profile

Premium Insights

The gold standard of business intelligence.

Find out more

Description

The project is currently owned by Luminant Generation with a stake of 100%.

It is a Combined Cycle Gas Turbine (CCGT) power plant. The fuel is procured from Kinder Morgan.

The project generated 7,796,751MWh of electricity.

Development status

The project got commissioned in February 2003.

Contractors involved

Forney Energy Center (Forney Energy Center Block I Unit I) is equipped with GE Power 7F.04 gas turbine. The phase consists of 1 gas turbine with 188.2MW nameplate capacity.

Forney Energy Center (Forney Energy Center Block I Unit II) is equipped with GE Power 7F.04 gas turbine. The phase consists of 1 gas turbine with 188.2MW nameplate capacity.

Forney Energy Center (Forney Energy Center Block I Unit III) is equipped with GE Power 7F.04 gas turbine. The phase consists of 1 gas turbine with 188.2MW nameplate capacity.

Forney Energy Center (Forney Energy Center Block I Unit IV) is equipped with Toshiba Energy Systems and Solutions steam turbine. The phase consists of 1 steam turbine with 382.5MW nameplate capacity.

Forney Energy Center (Forney Energy Center Block II Unit I) is equipped with GE Power 7F.04 gas turbine. The phase consists of 1 gas turbine with 188.2MW nameplate capacity.

Forney Energy Center (Forney Energy Center Block II Unit II) is equipped with GE Power 7F.04 gas turbine. The phase consists of 1 gas turbine with 188.2MW nameplate capacity.

Forney Energy Center (Forney Energy Center Block II Unit III) is equipped with GE Power 7F.04 gas turbine. The phase consists of 1 gas turbine with 188.2MW nameplate capacity.

Forney Energy Center (Forney Energy Center Block II Unit IV) is equipped with Toshiba Energy Systems and Solutions steam turbine. The phase consists of 1 steam turbine with 382.5MW nameplate capacity.

John Cockerill Group supplied steam boiler for the Forney Energy Center (Forney Energy Center Block I Unit I).

John Cockerill Group supplied steam boiler for the Forney Energy Center (Forney Energy Center Block I Unit II).

John Cockerill Group supplied steam boiler for the Forney Energy Center (Forney Energy Center Block I Unit III).

John Cockerill Group supplied steam boiler for the Forney Energy Center (Forney Energy Center Block II Unit I).

John Cockerill Group supplied steam boiler for the Forney Energy Center (Forney Energy Center Block II Unit II).

John Cockerill Group supplied steam boiler for the Forney Energy Center (Forney Energy Center Block II Unit III).

For more details on Forney Energy Center, buy the profile here.

This content was updated on 4 January 2024

Premium Insights

From

The gold standard of business intelligence.

Blending expert knowledge with cutting-edge technology, GlobalData’s unrivalled proprietary data will enable you to decode what’s happening in your market. You can make better informed decisions and gain a future-proof advantage over your competitors.

GlobalData

GlobalData, the leading provider of industry intelligence, provided the underlying research used to produce this article.

This information is drawn from GlobalData’s Power Intelligence Center, which provides detailed profiles of over 170,000 active, planned and under construction power plants worldwide from announcement through to operation across all technologies and countries worldwide.