Fujian Putian Nanri Longyuan Wind Farm is a 48.45MW onshore wind power project. It is located in Fujian, China. The project is currently active. It has been developed in single phase. Post completion of construction, the project got commissioned in November 2010.

Project Type Total Capacity (MW) Active Capacity (MW) Pipeline Capacity (MW) Project Status Project Location Project Developer
Onshore 48.45 48.45 Active Fujian, China

Description

The project is currently owned by China Longyuan Power Group.

The project generates 139,250MWh electricity thereby offsetting 115,926t of carbon dioxide emissions (CO2) a year. The project cost is $87.878m.

Development Status

The project is currently active. The project got commissioned in November 2010.

Contractors Involved

Siemens Gamesa Renewable Energy was selected as the turbine supplier for the wind power project. The company provided 57 units of G52-850 kW turbines, each with 0.85MW nameplate capacity.

Methodology

All power projects included in this report are drawn from GlobalData’s Power Intelligence Center. The information regarding the project parameters is sourced through secondary information sources such as electric utilities, equipment manufacturers, developers, project proponent’s – news, deals and financial reporting, regulatory body, associations, government planning reports and publications. Wherever needed the information is further validated through primary from various stakeholders across the power value chain and professionals from leading players within the power sector.