Futtsu Combined Cycle Power Plant is a 5,337MW gas fired power project. It is located in Chiba, Japan. The project is currently active. It has been developed in multiple phases. Post completion of construction, the project got commissioned in November 1986.
Project Type | Total Capacity (MW) | Active Capacity (MW) | Pipeline Capacity (MW) | Project Status | Project Location | Project Developer | Thermal | 5,337 | 5,337 | – | Active | Chiba, Japan |
---|
Description
The project is currently owned by JERA.
It is a combined cycle gas turbine (ccgt) power plant.
Futtsu Combined Cycle Power Plant (Futtsu Combined Cycle Power Plant Group I) consists of 7 turbines.
Futtsu Combined Cycle Power Plant (Futtsu Combined Cycle Power Plant Group I) consists of 7 turbines.
Futtsu Combined Cycle Power Plant (Futtsu Combined Cycle Power Plant Group III) consists of 4 turbines with 131MW nameplate capacity.
Development Status
The project got commissioned in November 1986.
Contractors Involved
Futtsu Combined Cycle Power Plant (Futtsu Combined Cycle Power Plant Group II) is equipped with GE Power turbines. The Gas fired phase consists 7 turbines.
Futtsu Combined Cycle Power Plant (Futtsu Combined Cycle Power Plant Group II) is equipped with Mitsubishi Power H-100(110)* – 50Hz turbines. The phase consists of 7 turbines.
Futtsu Combined Cycle Power Plant (Futtsu Combined Cycle Power Plant Group III) is equipped with GE Power MS9001FA++ turbines. The phase consists of 4 turbines with 249MW nameplate capacity.
Futtsu Combined Cycle Power Plant (Futtsu Combined Cycle Power Plant Group IV) is equipped with GE Power 1×1 SS 9HA.01 turbines. The phase consists of 3 turbines with 336MW nameplate capacity.
Futtsu Combined Cycle Power Plant (Futtsu Combined Cycle Power Plant Group IV) is equipped with Toshiba Energy Systems and Solutions Tandem Compound 2 Casing Double-flow, Reheat Condensing Type turbines. The phase consists of 3 turbines with 171MW nameplate capacity.
GE Power supplied electric generator for the Futtsu Combined Cycle Power Plant (Futtsu Combined Cycle Power Plant Group IV).
Toshiba Energy Systems and Solutions supplied Three-Phase AC Water Cooled Synchronous electric generator for the Futtsu Combined Cycle Power Plant (Futtsu Combined Cycle Power Plant Group IV).
GE Power supplied steam boiler for the Futtsu Combined Cycle Power Plant (Futtsu Combined Cycle Power Plant Group I).
GE Power supplied steam boiler for the Futtsu Combined Cycle Power Plant (Futtsu Combined Cycle Power Plant Group II).
IHI supplied steam boiler for the Futtsu Combined Cycle Power Plant (Futtsu Combined Cycle Power Plant Group III).
IHI supplied steam boiler for the Futtsu Combined Cycle Power Plant (Futtsu Combined Cycle Power Plant Group IV).
Methodology
All power projects included in this report are drawn from GlobalData’s Power Intelligence Center. The information regarding the project parameters is sourced through secondary information sources such as electric utilities, equipment manufacturers, developers, project proponent’s – news, deals and financial reporting, regulatory body, associations, government planning reports and publications. Wherever needed the information is further validated through primary from various stakeholders across the power value chain and professionals from leading players within the power sector.