Gardikfors is a 60MW hydro power project. It is located on Ume river/basin in Vasterbotten, Sweden. The project is currently active. It has been developed in single phase. The project construction commenced in 1959 and subsequently entered into commercial operation in 1963.

Project Type Total Capacity (MW) Active Capacity (MW) Pipeline Capacity (MW) Project Status Project Location Project Developer
Hydropower 60 60 Active Vasterbotten, Sweden

Description

The project is currently owned by Vattenfall with a stake of 100%.

The hydro reservoir capacity is 871 million cubic meter. The gross head of the project is 43m. The project generated 287 GWh of electricity.

The hydro power project consists of 1 turbine with 60MW nameplate capacity.

Development Status

The project construction commenced in 1959 and subsequently entered into commercial operation in 1963.

Contractors Involved

GenerPro supplied 1 electric generator for the project. The generator capacity is 60 MVA.

Methodology

All power projects included in this report are drawn from GlobalData’s Power Intelligence Center. The information regarding the project parameters is sourced through secondary information sources such as electric utilities, equipment manufacturers, developers, project proponent’s – news, deals and financial reporting, regulatory body, associations, government planning reports and publications. Wherever needed the information is further validated through primary from various stakeholders across the power value chain and professionals from leading players within the power sector.