Ginestra degli Schiavoni_ERG is a 40MW onshore wind power project. It is located in Campania, Italy. The project is currently active. It has been developed in single phase. Post completion of construction, the project got commissioned in June 2011.
Project Type | Total Capacity (MW) | Active Capacity (MW) | Pipeline Capacity (MW) | Project Status | Project Location | Project Developer | Onshore | 40 | 40 | – | Active | Campania, Italy |
---|
Description
The project is currently owned by ERG Power Generation.
The project cost is $125.36m.
Development Status
The project is currently active. The project got commissioned in June 2011.
Contractors Involved
Senvion was selected as the turbine supplier for the wind power project. The company provided 20 units of MM92 turbines, each with 2MW nameplate capacity.
Senvion is the O&M contractor for the wind power project. The operation and maintenance contract commenced from 2011, for a period of 13 years.
Methodology
All power projects included in this report are drawn from GlobalData’s Power Intelligence Center. The information regarding the project parameters is sourced through secondary information sources such as electric utilities, equipment manufacturers, developers, project proponent’s – news, deals and financial reporting, regulatory body, associations, government planning reports and publications. Wherever needed the information is further validated through primary from various stakeholders across the power value chain and professionals from leading players within the power sector.