Greenup Hydro is a 70.2MW hydro power project. It is located on Ohio river/basin in Ohio, the US. The project is currently active. It has been developed in single phase. Post completion of construction, the project got commissioned in 1982.

Project Type Total Capacity (MW) Active Capacity (MW) Pipeline Capacity (MW) Project Status Project Location Project Developer
Hydropower 70.2 70.2 Active Ohio, the US

Description

City of Hamilton and American Municipal Power are currently owning the project having ownership stake of 51.4% and 48.6% respectively.

Greenup Hydro is a run-of-river project. The project generated 282 GWh of electricity.

Development Status

The project got commissioned in 1982.

Contractors Involved

GE Renewable Energy was selected as the turbine supplier for the hydro power project. The company provided 3 units of kaplan turbines, each with 23.4MW nameplate capacity.

Methodology

All power projects included in this report are drawn from GlobalData’s Power Intelligence Center. The information regarding the project parameters is sourced through secondary information sources such as electric utilities, equipment manufacturers, developers, project proponent’s – news, deals and financial reporting, regulatory body, associations, government planning reports and publications. Wherever needed the information is further validated through primary from various stakeholders across the power value chain and professionals from leading players within the power sector.