Guizhou Pannan Power Plant Phase I is a 2,400MW coal fired power project. It is located in Guizhou, China. The project is currently active. It has been developed in multiple phases. Post completion of construction, the project got commissioned in December 2005.
Project Type | Total Capacity (MW) | Active Capacity (MW) | Pipeline Capacity (MW) | Project Status | Project Location | Project Developer | Thermal | 2,400 | 2,400 | – | Active | Guizhou, China |
---|
Description
Guangdong Energy Group and Guizhou Xidian Power are currently owning the project.
It is a steam turbine power plant.
Development Status
The project got commissioned in December 2005.
Contractors Involved
Dongfang Boiler Group supplied steam boiler for the Guizhou Pannan Power Plant Phase I (Guizhou Pannan Power Plant Phase I Unit I).
Dongfang Boiler Group supplied steam boiler for the Guizhou Pannan Power Plant Phase I (Guizhou Pannan Power Plant Phase I Unit II).
Shanghai Boiler Works supplied steam boiler for the Guizhou Pannan Power Plant Phase I (Guizhou Pannan Power Plant Phase I Unit III).
Shanghai Boiler Works supplied steam boiler for the Guizhou Pannan Power Plant Phase I (Guizhou Pannan Power Plant Phase I Unit IV).
Methodology
All power projects included in this report are drawn from GlobalData’s Power Intelligence Center. The information regarding the project parameters is sourced through secondary information sources such as electric utilities, equipment manufacturers, developers, project proponent’s – news, deals and financial reporting, regulatory body, associations, government planning reports and publications. Wherever needed the information is further validated through primary from various stakeholders across the power value chain and professionals from leading players within the power sector.