Huaneng Nantong Power Plant is a 2,454MW coal fired power project. It is located in Jiangsu, China. The project is currently active. It has been developed in multiple phases. Post completion of construction, the project got commissioned in September 1989.
Project Type | Total Capacity (MW) | Active Capacity (MW) | Pipeline Capacity (MW) | Project Status | Project Location | Project Developer | Thermal | 2,454 | 2,454 | – | Active | Jiangsu, China |
---|
Description
The project is currently owned by Huaneng Power International.
It is a steam turbine power plant.
Huaneng Nantong Power Plant (Huaneng Nantong Power Plant Phase III) consists of 1 steam turbine with 1,050MW nameplate capacity.
Development Status
The project got commissioned in September 1989.
Power Purchase Agreement
The power generated from the project is sold to State Grid Jiangsu Electric Power under a power purchase agreement.
Contractors Involved
Huaneng Nantong Power Plant (Huaneng Nantong Power Plant Phase I Unit I) is equipped with GE Power steam turbine. The phase consists of 1 steam turbine with 352MW nameplate capacity.
Huaneng Nantong Power Plant (Huaneng Nantong Power Plant Phase I Unit II) is equipped with GE Power steam turbine. The phase consists of 1 steam turbine with 352MW nameplate capacity.
Huaneng Nantong Power Plant (Huaneng Nantong Power Plant Phase II Unit I) is equipped with GE Power steam turbine. The phase consists of 1 steam turbine with 350MW nameplate capacity.
Huaneng Nantong Power Plant (Huaneng Nantong Power Plant Phase II Unit II) is equipped with GE Power steam turbine. The phase consists of 1 steam turbine with 350MW nameplate capacity.
GE Power supplied electric generator for the Huaneng Nantong Power Plant (Huaneng Nantong Power Plant Phase I Unit I).
GE Power supplied electric generator for the Huaneng Nantong Power Plant (Huaneng Nantong Power Plant Phase I Unit II).
GE Power supplied electric generator for the Huaneng Nantong Power Plant (Huaneng Nantong Power Plant Phase II Unit I).
GE Power supplied electric generator for the Huaneng Nantong Power Plant (Huaneng Nantong Power Plant Phase II Unit II).
Babcock & Wilcox Enterprises supplied steam boiler for the Huaneng Nantong Power Plant (Huaneng Nantong Power Plant Phase I Unit I).
Babcock & Wilcox Enterprises supplied steam boiler for the Huaneng Nantong Power Plant (Huaneng Nantong Power Plant Phase I Unit II).
Babcock & Wilcox Enterprises supplied steam boiler for the Huaneng Nantong Power Plant (Huaneng Nantong Power Plant Phase II Unit I).
Babcock & Wilcox Enterprises supplied steam boiler for the Huaneng Nantong Power Plant (Huaneng Nantong Power Plant Phase II Unit II).
Methodology
All power projects included in this report are drawn from GlobalData’s Power Intelligence Center. The information regarding the project parameters is sourced through secondary information sources such as electric utilities, equipment manufacturers, developers, project proponent’s – news, deals and financial reporting, regulatory body, associations, government planning reports and publications. Wherever needed the information is further validated through primary from various stakeholders across the power value chain and professionals from leading players within the power sector.