Inner Mongolia Chifeng Wengniute Wind Farm is a 48MW onshore wind power project. It is located in Inner Mongolia, China. The project is currently active. It has been developed in single phase. Post completion of construction, the project got commissioned in July 2011.
Project Type | Total Capacity (MW) | Active Capacity (MW) | Pipeline Capacity (MW) | Project Status | Project Location | Project Developer | Onshore | 48 | 48 | – | Active | Inner Mongolia, China | Longyuan (Wengniute) New Energy |
---|
Description
The project was developed by Longyuan (Wengniute) New Energy and is currently owned by China Longyuan Power Group with a stake of 100%.
The project generates 120,050MWh electricity thereby offsetting 123,411t of carbon dioxide emissions (CO2) a year. The project cost is $67.54m.
Development Status
The project is currently active. The project got commissioned in July 2011.
Contractors Involved
Siemens Gamesa Renewable Energy was selected as the turbine supplier for the wind power project. The company provided 24 units of G80-2.0 MW turbines, each with 2MW nameplate capacity.
Methodology
All power projects included in this report are drawn from GlobalData’s Power Intelligence Center. The information regarding the project parameters is sourced through secondary information sources such as electric utilities, equipment manufacturers, developers, project proponent’s – news, deals and financial reporting, regulatory body, associations, government planning reports and publications. Wherever needed the information is further validated through primary from various stakeholders across the power value chain and professionals from leading players within the power sector.