Jahrom Combined Cycle Power Plant is a 1,434MW oil fired power project. It is located in Fars, Iran. The project is currently active. It has been developed in multiple phases. Post completion of construction, the project got commissioned in July 2007.
Project Type | Total Capacity (MW) | Active Capacity (MW) | Pipeline Capacity (MW) | Project Status | Project Location | Project Developer | Thermal | 1,434 | 1,434 | – | Active | Fars, Iran | Jahrom Power Generation |
---|
Description
The project is developed and owned by Jahrom Power Generation.
It is a combined cycle gas turbine (ccgt) power plant.
Development Status
The project got commissioned in July 2007.

US Tariffs are shifting - will you react or anticipate?
Don’t let policy changes catch you off guard. Stay proactive with real-time data and expert analysis.
By GlobalDataContractors Involved
MAPNA Combined Cycle Power plants Constraction & Development, Moshanir and Tanavob General Contractor were selected to render EPC services for the oil fired power project.
Jahrom Combined Cycle Power Plant (Jahrom Combined Cycle Power Plant Block I Unit I) is equipped with MAPNA Turbine Engineering & Manufacturing MGT-70 gas turbine. The phase consists of 1 gas turbine with 159MW nameplate capacity.
Jahrom Combined Cycle Power Plant (Jahrom Combined Cycle Power Plant Block I Unit II) is equipped with MAPNA Turbine Engineering & Manufacturing MGT-70 gas turbine. The phase consists of 1 gas turbine with 159MW nameplate capacity.
Jahrom Combined Cycle Power Plant (Jahrom Combined Cycle Power Plant Block I Unit III) is equipped with MAPNA Turbine Engineering & Manufacturing E-TYPE steam turbine. The phase consists of 1 steam turbine with 160MW nameplate capacity.
Jahrom Combined Cycle Power Plant (Jahrom Combined Cycle Power Plant Block II Unit I) is equipped with MAPNA Turbine Engineering & Manufacturing MGT-70 gas turbine. The phase consists of 1 gas turbine with 159MW nameplate capacity.
Jahrom Combined Cycle Power Plant (Jahrom Combined Cycle Power Plant Block II Unit II) is equipped with MAPNA Turbine Engineering & Manufacturing MGT-70 gas turbine. The phase consists of 1 gas turbine with 159MW nameplate capacity.
Jahrom Combined Cycle Power Plant (Jahrom Combined Cycle Power Plant Block II Unit III) is equipped with MAPNA Turbine Engineering & Manufacturing E-TYPE steam turbine. The phase consists of 1 steam turbine with 160MW nameplate capacity.
Jahrom Combined Cycle Power Plant (Jahrom Combined Cycle Power Plant Block III Unit I) is equipped with MAPNA Turbine Engineering & Manufacturing MGT-70 gas turbine. The phase consists of 1 gas turbine with 159MW nameplate capacity.
Jahrom Combined Cycle Power Plant (Jahrom Combined Cycle Power Plant Block III Unit II) is equipped with MAPNA Turbine Engineering & Manufacturing MGT-70 gas turbine. The phase consists of 1 gas turbine with 159MW nameplate capacity.
Jahrom Combined Cycle Power Plant (Jahrom Combined Cycle Power Plant Block III Unit III) is equipped with MAPNA Turbine Engineering & Manufacturing E-TYPE steam turbine. The phase consists of 1 steam turbine with 160MW nameplate capacity.
MAPNA Generator Engineering & Manufacturing supplied electric generator for the project.
Doosan Heavy Industries Vietnam supplied steam boiler for the project.
Saba Power is the O&M contractor for thermal power project.
Methodology
All power projects included in this report are drawn from GlobalData’s Power Intelligence Center. The information regarding the project parameters is sourced through secondary information sources such as electric utilities, equipment manufacturers, developers, project proponent’s – news, deals and financial reporting, regulatory body, associations, government planning reports and publications. Wherever needed the information is further validated through primary from various stakeholders across the power value chain and professionals from leading players within the power sector.