Receive our newsletter – data, insights and analysis delivered to you
  1. Market Data
January 12, 2022

Kalaburagi-Jodhpur Windfarms, India

By Carmen

Kalaburagi-Jodhpur Windfarms is a 60MW onshore wind power project. It is located in Karnataka, India. The project is currently active. It has been developed in single phase. Post completion of construction, the project got commissioned in March 2018.

Project Type Total Capacity (MW) Active Capacity (MW) Pipeline Capacity (MW) Project Status Project Location Project Developer
Onshore 60 60 Active Karnataka, India Torrent Power

Description

The project is developed and owned by Torrent Power.

The project cost is $69.6m.

The project has 106m high towers.

Development Status

Content from our partners
How Hengst helped to keep Germany’s charity “star singers” shining
How one power station prevented frequent shutdowns with three-stage air filtration
Reimagining the carbon problem

The project is currently active. The project got commissioned in March 2018.

Contractors Involved

Siemens Gamesa Renewable Energy was selected as the turbine supplier for the wind power project. The company provided 30 turbines, each with 2MW nameplate capacity.

About Torrent Power

Torrent Power Ltd (Torrent Power), a subsidiary of Torrent Group, is a power utility that generates, transmits and distributes electricity. The company generates electricity through gas based, coal based and renewable power plants. It transmits and distributes power to residential, commercial and industrial customers in Ahmedabad, Gandhinagar, Surat and Dahej SEZ as well as Dholera SIR in Gujarat; Bhiwandi in Maharashtra; and in Agra in Uttar Pradesh. The company offers highly personalized as well as innovative customer services for better experience and customer satisfaction. It also manufactures cables through its cables manufacturing unit at Nadiad, Gujarat. Torrent Power is headquartered in Ahmedabad, Gujarat, India.

Methodology

All power projects included in this report are drawn from GlobalData’s Power Intelligence Center. The information regarding the project parameters is sourced through secondary information sources such as electric utilities, equipment manufacturers, developers, project proponent’s – news, deals and financial reporting, regulatory body, associations, government planning reports and publications. Wherever needed the information is further validated through primary from various stakeholders across the power value chain and professionals from leading players within the power sector.

Related Companies

NEWSLETTER Sign up Tick the boxes of the newsletters you would like to receive. The top stories of the day delivered to you every weekday. A weekly roundup of the latest news and analysis, sent every Wednesday. The power industry's most comprehensive news and information delivered every month.
I consent to GlobalData UK Limited collecting my details provided via this form in accordance with the Privacy Policy
SUBSCRIBED

THANK YOU