Kariba North, Zambia

By Carmen

Kariba North is a 720MW hydro power project. It is located on Zambezi river/basin in Zambia. The project is currently active. It has been developed in single phase. Post completion of construction, the project got commissioned in 1959.

Project Type Total Capacity (MW) Active Capacity (MW) Pipeline Capacity (MW) Project Status Project Location Project Developer
Hydropower 720 720 Active Zambia Webuild

Description

The project was developed by Webuild and is currently owned by ZESCO.

Kariba North is a reservoir based project. The gross head of the project is 92m. Kariba North underwent through rehabilitation & modernization during 2000-2009, 2009-2012.

Development Status

The project got commissioned in 1959.

Content from our partners
Green investment: What gives Scotland multiple advantages
How Hengst helped to keep Germany’s charity “star singers” shining
How one power station prevented frequent shutdowns with three-stage air filtration

Contractors Involved

Andritz Hydro was selected as the turbine supplier for the hydro power project. The company provided 4 turbines, each with 180MW nameplate capacity.

Koncar – Elektroindustrija supplied 4 electric generators for the project.

About Webuild

Webuild SpA (Webuild), formerly Salini Impregilo SpA, is a heavy construction contractor. It specializes in executing large and complex projects. The company offers design, engineering and construction services for dams, hydroelectric plants, canals, railways, metros, bridges, roads, motorways, civil and industrial buildings and airports. It also executes underground works, and civil engineering works for waste-to-energy plants and environmental protection projects. The company also carries out concessions activities related to motorways, metros and car parks. Webuild primarily serves water, renewable energy, transport and urban infrastructure sectors. It has operations in several countries across Europe, North America, Latin America, the Middle East, Africa, Asia and Oceania. Webuild is headquartered in Milan, Italy.

Methodology

All power projects included in this report are drawn from GlobalData’s Power Intelligence Center. The information regarding the project parameters is sourced through secondary information sources such as electric utilities, equipment manufacturers, developers, project proponent’s – news, deals and financial reporting, regulatory body, associations, government planning reports and publications. Wherever needed the information is further validated through primary from various stakeholders across the power value chain and professionals from leading players within the power sector.

Related Companies

NEWSLETTER Sign up Tick the boxes of the newsletters you would like to receive. The top stories of the day delivered to you every weekday. A weekly roundup of the latest news and analysis, sent every Wednesday. The power industry's most comprehensive news and information delivered every month.
I consent to GlobalData UK Limited collecting my details provided via this form in accordance with the Privacy Policy
SUBSCRIBED

THANK YOU